summaryrefslogtreecommitdiff
path: root/21083-0.txt
diff options
context:
space:
mode:
Diffstat (limited to '21083-0.txt')
-rw-r--r--21083-0.txt3355
1 files changed, 3355 insertions, 0 deletions
diff --git a/21083-0.txt b/21083-0.txt
new file mode 100644
index 0000000..14ea1e8
--- /dev/null
+++ b/21083-0.txt
@@ -0,0 +1,3355 @@
+The Project Gutenberg EBook of Transactions of the American Society of
+Civil Engineers, vol. LXVIII, Sept. 191, by F. Lavis
+
+This eBook is for the use of anyone anywhere at no cost and with
+almost no restrictions whatsoever. You may copy it, give it away or
+re-use it under the terms of the Project Gutenberg License included
+with this eBook or online at www.gutenberg.org
+
+
+Title: Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910
+ The Bergen Hill Tunnels. Paper No. 1154
+
+Author: F. Lavis
+
+Release Date: April 15, 2007 [EBook #21083]
+
+Language: English
+
+Character set encoding: UTF-8
+
+*** START OF THIS PROJECT GUTENBERG EBOOK SOCIETY OF CIVIL ENGINEERS ***
+
+
+
+
+Produced by Louise Hope, Juliet Sutherland and the Online
+Distributed Proofreading Team at http://www.pgdp.net
+
+
+
+
+
+
+ [Transcriber’s Note:
+
+ Two other papers from ASCE _Transactions_ LXVIII (September 1910) are
+ referenced in this paper:
+
+ No. 1150, “The New York Tunnel Extension...” by Charles W. Raymond,
+ available from Project Gutenberg as e-text #18229.
+
+ No. 1151, “The North River Division” by Charles M. Jacobs, e-text
+ #18548, generally cited as “the paper by Mr. Jacobs”.
+
+ The word “Figure” is used in two ways. It refers either to individual
+ numbered Figures (1-21), or to any of the four pictures that make up
+ each Plate, identified in the form “Fig. 2, Plate XXI”. Figures 1-4
+ are always discussed as a group.
+
+ Single letters in boldface are shown as =A=. Typographical errors are
+ listed at the end of the text.]
+
+ * * * * *
+ * * * *
+ * * * * *
+
+ American Society of Civil Engineers
+ Instituted 1852
+ TRANSACTIONS
+
+ Paper No. 1154
+
+ THE NEW YORK TUNNEL EXTENSION OF THE PENNSYLVANIA RAILROAD.
+ THE BERGEN HILL TUNNELS.[1]
+
+ By F. LAVIS, M. Am. Soc. C. E.
+
+ [Footnote 1: Presented at the meeting of April 6th, 1910.]
+
+
+_Location._--That section of the Pennsylvania Railroad’s New York
+Tunnels lying west of the Hudson River is designated Section “K,” and
+the tunnels are generally spoken of as the Bergen Hill Tunnels. Bergen
+Hill is a trap dike (diabase) forming the lower extension of the Hudson
+River Palisades.
+
+There are two parallel single-track tunnels, cross-sections of which are
+shown on Plate VIII of the paper by Charles M. Jacobs, M. Am. Soc. C. E.
+The center line is a tangent, and nearly on the line of 32d Street, New
+York City, produced, its course being N. 50° 30' W. The elevation of the
+top of the rail at the Weehawken Shaft (a view of which is shown by
+Fig. 2, Plate XXII), on the west bank of the Hudson River, is about 64
+ft. below mean high water; and at the Western Portal, or Hackensack end,
+the rail is about 17 ft. above; the grade throughout is 1.3%, ascending
+from east to west. The length of each tunnel between the portals is
+5,920 ft.
+
+A general plan and profile of these tunnels is shown on Plate I of the
+paper by Charles W. Raymond, M. Am. Soc. C. E. At Central Avenue a shaft
+212 ft. deep was sunk. It is 3,620 ft. from the Weehawken Shaft.
+
+ [Illustration: Plate XXI.
+ Fig. 1: K 94. P.R.R. Tunnels, N. R. D. Section K. (Bergen Hill
+ Tunnels.) from Hackensack Poral, North Cut and Cover Section, and
+ Portal looking East from Sta. 323. Dec. 8, 05.
+ Fig. 2: K 71. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Method of using Cross-Section Rod in getting Sections of
+ Tunnel. Aug. 30, 06.
+ Fig. 3: K 115. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, North Tunnel Conveyor used by King Rice
+ and Garney for handling and placing concrete. June 3, 07.
+ Fig. 4: K 116. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, North Tunnel. View of conveyor for placing
+ concrete, with bucket suspended over hopper above belt. Steel forms
+ in fore ground. June 4, 07.]
+
+
+_History._--The contract for this work was let on March 6th, 1905, to
+the John Shields Construction Company; it was abandoned by the Receiver
+for that company on January 20th, 1906, and on March 20th, of that year,
+was re-let to William Bradley, who completed the work by December 31st,
+1908.
+
+The progress of excavation and lining in the North Tunnel is shown
+graphically on the progress diagram, Fig. 9, that of the South Tunnel
+being practically the same.
+
+
+_Geology._--Starting west from the Weehawken Shaft, the tunnels pass
+through a wide fault for a distance of nearly 400 ft., this fault being
+a continuation of that which forms the valley between the detached mass
+of trap and sandstone known as King’s Bluff, which lies north of the
+tunnels, and the main trap ridge of Bergen Hill.
+
+The broken ground of the fault, which consists of decomposed sandstone,
+shale, feldspar, calcite, etc., interspersed with masses of harder
+sandstone and baked shale, gradually merges into a compact granular
+sandstone, which, at a distance of 460 ft. from the shaft, was
+self-supporting, and did not require timbering, which, of course, had
+been necessary up to this point.
+
+A full face of sandstone continued to Station 274 + 60, 940 ft. from the
+shaft, where the main overlying body of trap appeared in the heading.
+The full face of the tunnel was wholly in trap at about Station 275 +
+30, and continued in this through to the Western Portal, where the top
+of the trap was slightly below the roof of the tunnel, with hardpan
+above. The contact between the sandstone and the overlying trap was very
+clearly defined, the angle of dip being approximately 17° 40' toward the
+northwest.
+
+The sandstone and trap are of the Triassic Period, and the trap of this
+vicinity is more particularly classified as diabase.
+
+The character of the trap rock varied considerably. At the contact,
+at Station 275, and for a distance of approximately 200 ft. west,
+corresponding to a thickness of about 60 ft. measured at right angles to
+the line of the contact, a very hard, fine-grained trap, almost black in
+color, was found, having a specific gravity of 2.98, and weighing 186
+lb. per cu. ft. The hardness of this rock is attested by the fact that
+the average time required to drill a 10-ft. hole in the heading, with a
+No. 34 slugger drill, with air at 90 lb. pressure, was almost 10 hours.
+The specific gravity of this rock is not as high as that of some other
+specimens of trap tested, which were much more easily drilled. This rock
+was very blocky, causing the drills to bind and stick badly, and, when
+being shoveled back from the heading, as it fell it sounded very much as
+though it were broken glass.
+
+The remainder of the trap varied from this, through several changes of
+texture and color, due to different amounts of quartz and feldspar, to a
+very coarse-grained rock, closely resembling granite of a light color,
+though quite hard. The speed of drilling the normal trap in the heading
+was approximately 20 to 25 min. per ft., as compared with the 60 min.
+per ft. noted above, the larger amounts of quartz and feldspar
+accounting for the greater brittleness and consequently the easier
+drilling qualities of the rock. The normal trap in these tunnels has a
+specific gravity varying from 2.85 to 3.04, and weighs from 179 to 190
+lb. per cu. ft.
+
+The temperature of the tunnels, at points 1,000 ft. from the portals at
+both ends, remained nearly stationary, and approximately between 50° in
+winter and 60° in summer, up to the time the headings were holed
+through, being practically unaffected by daily changes in the
+temperature outside. At the western end, after the connection with the
+Central Shaft headings was made, there was almost always a current of
+air from the portal to the shaft, and ascending through the latter. This
+tended to make the temperature in this part of the tunnel correspond
+more nearly with the outside temperature; in fact, the variation was
+seldom more than 5° Fahr.
+
+
+_Timbering._--These tunnels have been excavated entirely by the center
+top heading method, almost invariably used in the United States.
+Timbering, where required, was of the usual segmental form with outside
+lagging, as shown in several of the photographs. In a few places it was
+necessary to hold the ground as the work progressed, and, in such cases,
+crown bars were used in the headings.
+
+There was some little trouble at the Western Portal, where the top of
+the rock was very near the roof of the tunnel, as shown by Fig. 1, Plate
+XXI. A side heading was driven at the level of the springing line until
+a point was reached where the roof was self-supporting, and the
+timbering was brought out to the face of the portal from that point.
+
+ [Illustration: Plate XXII.
+ Fig. 1: K 26. P.R.R. Tunnels, N. R. D. Sect. K. (Bergen Hill
+ Tunnels,) Weehawken Shaft. Scaffold car in South Tunnel at Sta.
+ 267+60. Jan. 11, 06.
+ Fig. 2: K 31. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft. Headhouse at ? elevator frame work,
+ looking West. Oct. 17, 06.
+ Fig. 3.--Round Holes in Concrete Forms.
+ Fig. 4.--Round Holes in Concrete Forms Completed.]
+
+
+_Drilling._--Where no timbering was required, several different methods
+were used in drilling and excavating the solid rock, though in all cases
+a center top heading was driven. The four diagrams, Figs. 1, 2, 3,
+and 4, give typical examples of these methods and show, in the order of
+their numbers, the general tendency of the development from a small
+heading kept some distance ahead of the bench, to a large heading with
+the bench kept close to it. The notes on each diagram give the general
+details of the quantity of drilling and powder used, methods of
+blasting, etc., and on the progress profile, Fig. 6, is indicated those
+portions of the tunnels in which each method was used.
+
+All the drills used throughout the work by Mr. Bradley were Rand No. 34
+sluggers, with 3⅝-in. cylinders, and the steel was that known as the
+“Black Diamond Brand,” 1⅜-in., octagon. It was used in 2, 4, 6, 8, 10,
+and 12-ft. lengths; toward the end of the work it was proposed to use
+14-ft. lengths, but owing to some delay in delivery this length was
+never obtained. The starters, 18 to 24 in. long, were sharpened to 2¾ to
+3-in. gauge, which was generally held up to depths of 6 ft.; then the
+gauge gradually decreased until it was 1¾ to 2¼ in. at the bottom of a
+12-ft. hole. Frequently, as many as three or four starters were used in
+starting a hole, and generally two sharpenings were required for each
+2 ft. drilled, after the first 6 ft. It is estimated that about ¼ in. of
+steel was used for each sharpening, and that there was an average of one
+sharpening for every foot drilled.
+
+The total quantity of steel used up, lost, or scrapped on the whole work
+was almost exactly 1 ft. for each 10 cu. yd. excavated, equal to 1¼ in.
+of steel per yard, distributed approximately as follows:
+
+ Sharpening ¾ to ⅞ in.
+ Other losses ½ to ⅜ ”
+ ---------------
+ Total 1¼ in. per cu. yd.
+
+An “Ajax” drill sharpener was used, and proved very satisfactory. Rubber
+and cotton hose, covered with woven marlin, was used for the bench
+(3 in. inside diameter, in 50-ft. lengths), for drills (1 in. in
+diameter, in 25-ft. lengths), and for steam shovels (2½ in. in diameter,
+in 50-ft. lengths). Hose coverings of wound marlin, and of woven marlin
+with spiral steel wire covering were tried, but were not satisfactory,
+owing to the unwinding of the marlin and the bending of the steel
+covering.
+
+ [Illustration: Fig. 1. {Drilling Method No. 1}
+ CROSS-SECTION, LONGITUDINAL SECTION, PLAN]
+
+ Drilling Method No. 1: Small heading, 60 to 80 ft. long. Two columns
+ used in heading, with two drills on each. Drills on sub-bench and
+ main bench mounted on tripods.
+
+ +--------------------------------------------------+
+ | Per Round |
+ +---------+---------+---------+----------+---------+
+ | | Total | No. of | Pounds | |
+ | | Depth | Cubic | of | Advance |
+ | | Drilled | Yards | Dynamite | |
+ +---------+---------+---------+----------+---------+
+ | Heading | 140-155 | 18-21.6 | 93-131 | 5-6 |
+ +---------+---------+---------+----------+---------+
+ | Bench | 110-120 | 53-60 | 76-97 | 3½-4 |
+ +---------+---------+---------+----------+---------+
+
+ +---------+--------------------+-----------------------------+
+ | | Per Cubic Yard | Per linear Foot of Tunnel |
+ | +---------+----------+-------+---------+-----------+
+ | | Linear | Pounds | Cubic | No. of | Pounds |
+ | | Feet | of | Yards | Feet | of |
+ | | Drilled | Dynamite | | Drilled | Dynamite |
+ +---------+---------+----------+-------+---------+-----------+
+ | Heading | 8-9 | 5-6 | 3.6 | 29.-32 | 18-22 |
+ +---------+---------+----------+-------+---------+-----------+
+ | Bench | 2 | 1.4-1.6 | 15.4 | 30.-31 | 21.5-24.6 |
+ +---------+---------+----------+-------+---------+-----------+
+ | Total | 19 | 59.63 | 39.5-46.6 |
+ +------------------------------+-------+---------+-----------+
+ | Per cubic yard, whole tunnel section | 3 to 33 | 2.1-2.5 |
+ +--------------------------------------+---------+-----------+
+
+ +---------------------------------------------------+------------+
+ | | Number |
+ | Blasting Notes: | of Sticks |
+ | +------------+
+ | Heading: First Round: 6 sticks, 60% in each cut | |
+ | hole, cut generally blasted twice | 36 to 72 |
+ | Second Round: 3 side holes each side, | |
+ | 5 sticks, 40% ea. | 30 |
+ | Third Round: Rest of side holes and dry | |
+ | holes, 5 sticks, 40% each | 40 |
+ | Stub holes, say | 5 to 15 |
+ | +------------+
+ | Total Sticks | 111 to 157 |
+ | +------------+
+ | Total Pounds | 93 to 131 |
+ | +------------+
+ | Sub-bench: 4 widening holes; 2 to 3 sticks, | |
+ | each, 40% | 10 to 12 |
+ | 6 down holes; 5 to 7 sticks, each, 40% | 30 to 42 |
+ | Bench: 6 holes; 6 to 8 sticks each, 40% | 36 to 48 |
+ | Taking up bottom, average, say | 15 |
+ | +------------+
+ | Total Sticks | 91 to 117 |
+ | +------------+
+ | Total Pounds | 76 to 97 |
+ +---------------------------------------------------+------------+
+
+
+ [Illustration: Fig. 2.
+ CROSS-SECTION, LONGITUDINAL SECTION, PLAN]
+
+ Drilling Method, No. 2: Five drills in heading, mounted on three
+ columns; the holes marked with a cross (X) were drilled with the
+ drills on the center column.
+
+ +--------------------------------------------------+
+ | Per Round |
+ +---------+---------+---------+----------+---------+
+ | | Total | No. of | Pounds | |
+ | | Depth | Cubic | of | Advance |
+ | | Drilled | Yards | Dynamite | |
+ +---------+---------+---------+----------+---------+
+ | Heading | 190-220 | 35-42 | 134-196 | 6½-8 |
+ +---------+---------+---------+----------+---------+
+ | Bench | 110-130 | 55 | 79-106 | 4 |
+ +---------+---------+---------+----------+---------+
+
+ +---------+--------------------+-----------------------------+
+ | | Per Cubic Yard | Per linear Foot of Tunnel |
+ | +---------+----------+-------+---------+-----------+
+ | | Linear | Pounds | Cubic | No. of | Pounds |
+ | | Feet | of | Yards | Feet | of |
+ | | Drilled | Dynamite | | Drilled | Dynamite |
+ +---------+---------+----------+-------+---------+-----------+
+ | Heading | 5.4-6.0 | 3.9-5.0 | 5.3 |28 to 32.| 20.7-26.5 |
+ +---------+---------+----------+-------+---------+-----------+
+ | Bench | 2.-2.4 | 1.4-2.0 | 13.7 | 27.-33. | 19.2-27.4 |
+ +---------+---------+----------+-------+---------+-----------+
+ | Total | 19 | 55.-65. | 39.9-53.9 |
+ +------------------------------+-------+---------+-----------+
+ | Per cubic yard, whole tunnel section | 2.9-3.4 | 2.1-2.8 |
+ +--------------------------------------+---------+-----------+
+
+
+ +---------------------------------------------------+------------+
+ | | Number |
+ | Blasting Notes: | of Sticks |
+ | +------------+
+ | Heading: First Round; 2 to 3 relieving holes | |
+ | sprung with 4 to 5 sticks each | 8 to 15 |
+ | 8 cut holes, 7 sticks each | |
+ | (sometimes shot twice) | 56 to 112 |
+ | First side round, 6 holes, 6 sticks | |
+ | each | 36 |
+ | Widening and dry holes, 10 to 12, | |
+ | 6 sticks each | 60 to 72 |
+ | +------------+
+ | Total Sticks | 160 to 235 |
+ | +------------+
+ | Total Pounds | 134 to 196 |
+ | ----------------+------------+
+ | Sub-bench: 8 holes, 4 to 6 sticks, each | 32 to 48 |
+ | | |
+ | Bench: 8 holes, 6 to 8 sticks, each | 46 to 64 |
+ | Taking up bottom, average | 15 |
+ | +------------+
+ | Total Sticks | 95 to 127 |
+ | +------------+
+ | Total Pounds | 79 to 109 |
+ +---------------------------------------------------+------------+
+
+
+
+ [Illustration: Fig. 3.
+ CROSS-SECTION, LONGITUDINAL SECTION, PLAN]
+
+ Drilling Method No. 3: Heading same as second method, but larger lift
+ taken off bench, and lift holes drilled in bottom bench in order to
+ get down to grade in floor. Bench kept closer to heading.
+
+ +---------------------------------------------------------+
+ | Per Round |
+ +---------+------------+-----------+------------+---------+
+ | | Total | No. of | Pounds | |
+ | | Depth | Cubic | of | Advance |
+ | | Drilled | Yards | Dynamite | |
+ +---------+------------+-----------+------------+---------+
+ | Heading | 190 to 220 | 35 to 42 | 134 to 196 | 6½ to 8 |
+ +---------+------------+-----------+------------+---------+
+ | | | | | |
+ | Bench | 145 ” 190 | 90 to 110 | 118 ” 167 | 6½ ” 8 |
+ +---------+------------+-----------+------------+---------+
+
+ +-----+-------------------------+----------------------------------+
+ | | Per Cubic Yard | Per linear Foot of Tunnel |
+ | +------------+------------+-------+-----------+--------------+
+ | | Linear | Pounds | Cubic | No. of | Pounds |
+ | | Feet | of | Yards | Feet | of |
+ | | Drilled | Dynamite | | Drilled | Dynamite |
+ +-----+------------+------------+-------+-----------+--------------+
+ | Hd. | 5.4 to 6.0 | 3.9 to 5.0 | 5.3 | 28 to 32 | 20.7 to 26.5 |
+ +-----+------------+------------+-------+-----------+--------------+
+ | B. | 1.6 ” 1.9 | 1.3 ” 1.8 | 13.7 | 22 ” 36 | 17.8 ” 24.7 |
+ +-----+------------+------------+-------+-----------+--------------+
+ | Total | 19 | 50 ” 58 | 38.5 ” 51.2 |
+ +-------------------------------+-------+-----------+--------------+
+ | Per cubic yard, whole tunnel section | 2.6 ” 3.1 | 2.0 ” 2.6 |
+ +---------------------------------------+-----------+--------------+
+
+ +---------------------------------------------------+------------+
+ | | Number |
+ | Blasting Notes: | of Sticks |
+ | +------------+
+ | Heading: First Round: 2 to 3 relieving holes | |
+ | sprung, with 4 to 5 sticks each | 8 to 15 |
+ | 8 cut holes, 7 sticks each | |
+ | (sometimes shot twice) | 56 to 112 |
+ | First side round, 6 holes, 6 sticks | |
+ | each | 36 |
+ | Widening and dry holes, 10 to 12 holes, | |
+ | 6 sticks each | 60 to 72 |
+ +---------------------------------------------------+------------+
+ | Total Sticks | 160 to 235 |
+ +---------------------------------------------------+------------+
+ | Total Pounds | 134 to 196 |
+ +---------------------------------------------------+------------+
+ | | |
+ | Sub-bench: 4 widening holes, 4 to 5 sticks each, | |
+ | 2 rounds | 32 to 40 |
+ | 6 down holes, 5 to 7 sticks each, | |
+ | 2 rounds | 60 to 84 |
+ | | |
+ | Bench: 4 down holes, 5 to 7 sticks each | 20 to 28 |
+ | 6 to 8 lift holes, 5 to 6 sticks each | 30 to 48 |
+ +---------------------------------------------------+------------+
+ | Total Sticks | 142 to 200 |
+ +---------------------------------------------------+------------+
+ | Total Pounds | 118 to 167 |
+ +---------------------------------------------------+------------+
+
+
+ [Illustration: Fig. 4.
+ CROSS-SECTION, LONGITUDINAL SECTION, PLAN]
+
+ Drilling Method No. 4: 8 drills on 4 columns used in heading. Bench
+ taken off in one lift. Bottom taken up with lift holes.
+
+ +--------------------------------------------------+
+ | Per Round |
+ +---------+---------+---------+----------+---------+
+ | | Total | No. of | Pounds | |
+ | | Depth | Cubic | of | Advance |
+ | | Drilled | Yards | Dynamite | |
+ +---------+---------+---------+----------+---------+
+ | Heading | 310-320 | 63-71 | 215-257 | 8-9 |
+ +---------+---------+---------+----------+---------+
+ | Bench | 190-210 | 89-100 | 107-155 | 8-9 |
+ +---------+---------+---------+----------+---------+
+
+ +---------+--------------------+------------------------------+
+ | | Per Cubic Yard | Per linear Foot of Tunnel |
+ | +---------+----------+-------+----------+-----------+
+ | | Linear | Pounds | Cubic | No. of | Pounds |
+ | | Feet | of | Yards | Feet | of |
+ | | Drilled | Dynamite | | Drilled | Dynamite |
+ +---------+---------+----------+-------+----------+-----------+
+ | Heading | 4.5-5.1 | 3.4-5.7 | 7.9 | 35.6-45. | 26.9-45.0 |
+ +---------+---------+----------+-------+----------+-----------+
+ | Bench | 1.9-2.2 | 1.2-1.7 | 11.1 | 21.1-24. | 13.3-18.9 |
+ +---------+---------+----------+-------+----------+-----------+
+ | Total | 19 | 56.7-69. | 40.2-63.9 |
+ +------------------------------+-------+----------+-----------+
+ | Per cubic yard, whole tunnel section | 3.-3.6 | 2.1-3.4 |
+ +--------------------------------------+----------+-----------+
+
+ +---------------------------------------------------+------------+
+ | | Number |
+ | Blasting Notes: | of Sticks |
+ | | |
+ | All holes of whole round are cleaned and loaded | |
+ | before blasting is started | |
+ | | |
+ | First Round: 5-6 lift holes, 7 to 9 sticks each | 35 to 54 |
+ | First row, sub-bench, 6 holes, 6 to 8 | |
+ | sticks each | 36 to 48 |
+ | | |
+ | Second Round: Second row, sub-bench and widening | |
+ | holes, 8 to 10 holes, 6 to 8 sticks each | 48 to 64 |
+ | Stub holes | 10 to 20 |
+ | | |
+ | Bench: Total Sticks | 129 to 186 |
+ | Total Pounds | 107 to 155 |
+ | | |
+ | Third Round: 8 cut holes, 7 sticks each, often | |
+ | requires 3 to 4 charges | 112 to 224 |
+ | Fourth Round: 8 holes, First side round, 5 to 7 | |
+ | sticks each | 40 to 56 |
+ | Fifth Round: 8 holes, Second side round, 5 to 7 | |
+ | sticks each | 40 to 56 |
+ | 2 dry holes 5 to 7 sticks each | 10 to 14 |
+ | Sixth Round: 4 to 6 widening holes and dry holes, | |
+ | 6 sticks each | 36 to 48 |
+ | Stub holes | 20 to 30 |
+ | | |
+ | Heading: Total Sticks | 258 to 428 |
+ | Total Pounds | 215 to 357 |
+ +---------------------------------------------------+------------+
+
+
+The average quantity of powder used on the whole work was about 2.9 lb.
+per cu. yd. The tables on the diagrams, Figs. 1, 2, 3, and 4, show that
+the quantity actually used in making the advance at the main working
+faces was about 2.5 lb. The difference is accounted for by the larger
+percentage of powder used for trimming the sides, breaking out the
+cross-passages between the tunnels, and the excavation of the ditches,
+the latter operation not being done until the concrete lining was about
+to be put in.
+
+There was some time, too, during the earlier stages of the work, when it
+is believed that an excessive quantity of powder was used; for one or
+two months it ran up to 4 lb. per cu. yd.
+
+ [Illustration: Fig. 5.
+ MUCK CAR USED AT WEEHAWKEN SHAFT]
+
+The dynamite used was “Forcite.” At first, both 40% and 60% were used,
+the 60% generally only for blasting the cut in the headings; during the
+latter part of the work, however, the 60% was used exclusively.
+
+The rock as a rule broke very well, and only a comparatively small
+quantity could not be handled by the shovels without being broken up
+further by block-holing. In the sandstone the quantity of powder per
+cubic yard was much more than for any of the trap.
+
+In drilling the Central Shaft, a 6-hole cut was made approximately on
+the center line, east and west, the enlargement requiring about 18 more
+holes, which were generally about 6 ft. deep, the average advance being
+about 4 ft. per day of 24 hours.
+
+ [Illustration: Fig. 6.
+ PROGRESS PROFILES OF NORTH AND SOUTH TUNNELS SHOWING MONTHLY
+ EXCAVATION]
+
+The drills were run by steam until a depth of about 150 ft. had been
+reached, air from the plant at Hackensack being available after that
+time. Four drills were used most of the time, and six later when air was
+available. This work was done entirely by the John Shields Construction
+Company, and a depth of 205 ft. was sunk in 6 months (from July 15th,
+1905, to January 15th, 1906). A derrick was used for hoisting and
+lowering men and tools during the sinking, elevators being put in later.
+
+
+ [Illustration:
+ PLATE XXIII.]
+
+_Drilling Data._--During the progress of the work, both general and
+detailed observations were made of the drilling, the results of which
+are shown in the tables. Table 1 has been compiled from the records as
+platted daily on the chart from the inspectors’ reports, as shown by
+Plate XXIII, and described on page 113. Table 2 contains some data
+relating to the drilling in the headings.
+
+The general results of these observations show that the average time the
+drills were “actually working” was 5.2 hours per shift, and that they
+were actually “hitting the rock” about half of this time, or about 2.5
+hours per shift. The average depth drilled per hour, during the time the
+drills were “actually working,” was 2.66 ft.
+
+The “actual working time,” as noted above, covers the period from the
+time the drills were first set up in the heading after blasting until
+they were taken down for the next blast; it does not include the time
+occupied in setting up or taking down, which would probably average 30
+min. more per shift. It is believed that this figure will also apply
+very closely to drills working on the bench, though no actual
+observations were taken to determine this, on account of the
+irregularity with which they were worked.
+
+The actual working time of the drills in the 736 shifts (7,360 hours)
+covered by Table 1, was 3,826 hours, or 5.2 hours per shift. The average
+depth drilled per yard, as shown in the last column of Table 1, agrees
+fairly well with the figures on the diagrams, Figs. 1, 2, 3, and 4.
+
+Table 2 has been compiled from detailed timed observations of individual
+drilling of down holes in the bench, for periods of 7 or 8 hours each,
+in January, 1907. The work at that time was in fairly normal condition
+at all points.
+
+The figures in the third column of Table 2 include the time required for
+moving from one hole to another, when this occurred during the
+observation, the time required for changing bits, oiling drills, etc.,
+and all delays of all kinds. A close record of the delays was kept, and
+it was considered that, of the 93 hours, 48 min., in Table 2, the
+unnecessary delays amounted to 5 hours, 7 min., or about 5½ per cent.
+
+ TABLE 1.
+
+ #S. Number of shifts covered by observations.
+ #Hrs Average number of hours worked per shift.
+ D/Hr Average depth drilled per hour per drill.
+ D/Yd Average depth drilled per yard.
+ Hack. Hackensack
+ Whk. Weehawken
+ CS Central Shaft
+
+ ----------------+-----------+----+-----------+------+------+------
+ Method. | Date. | #S | Place. | #Hrs | D/Hr | D/Yd
+ ----------------+-----------+----+-----------+------+------+------
+ {| Aug. ’06 | 44 | Hack., N. | 5.69 | 2.78 | 10.1
+ {| Sept. ’06 | 38 | ” N. | 5.80 | 3.77 | 11.1
+ No. 1-- {| Aug. ’06 | 43 | ” S. | 5.60 | 2.89 | 9.1
+ 4-drill {| Sept. ’06 | 36 | ” S. | 6.18 | 2.65 | 8.7
+ {| Jan. ’07 | 16 | CS E. N. | 5.99 | 2.99 | 8.2
+ {| Jan. ’07 | 20 | ” S. | 6.05 | 2.9 | 7.1
+ {| Apr. ’07 | 48 | CS W. N. | 4.92 | 3.3 | 6.7
+ {| Apr. ’07 | 48 | ” S. | 5.00 | 3.2 | 7.7
+ | | | | | |
+ {| Dec. ’06 | 54 | Whk., N. | 4.95 | 2.16 | 4.52
+ Nos. 2 and 3-- {| Dec. ’06 | 54 | ” S. | 5.23 | 2.14 | 4.54
+ 5-drill {| Dec. ’06 | 52 | Hack., N. | 5.03 | 2.2 | 5.77
+ {| Dec. ’06 | 54 | ” S. | 5.90 | 1.82 | 5.67
+ | | | | | |
+ No. 4-- {| June ’07 | 56 | Whk., N. | 4.77 | 2.55 | 4.23
+ 7-drill {| June ’07 | 58 | ” S. | 4.82 | 2.26 | 3.88
+ | | | | | |
+ 8-drill {| May ’07 | 60 | Hack., N. | 4.67 | 2.44 | 5.00
+ {| May ’07 | 60 | ” S. | 4.54 | 2.57 | 4.80
+ ----------------+-----------+----+-----------+------+------+------
+
+
+ TABLE 2.
+
+ Hrs. _Hours._
+ Min. _Minutes._
+
+ ----------------+----------+---------------+----------------
+ Date. | Place. | Total | Number of feet
+ | | working time. | drilled.
+ ----------------+----------+---------------+----------------
+ | | Hrs. Min. |
+ Jan. 14th, 1907 | Whk. N. | 8 0 | 15
+ ” 15th, 1907 | ” N. | 7 32 | 12
+ | ” N. | 7 22 | 14
+ ” 12th, 1907 | ” S. | 8 0 | 20
+ | ” S. | 8 0 | 11
+ | ” S. | 8 0 | 10
+ ” 11th, 1907 | Hack. N. | 8 0 | 13
+ ” 17th, 1907 | ” N. | 7 10 | 10
+ | ” N. | 7 5 | 11
+ | ” N. | 7 10 | 10
+ ” 16th, 1907 | ” S. | 4 20 | 10
+ | ” S. | 6 9 | 10
+ | ” S. | 7 ... | 8
+ ----------------+----------+---------------+---------------
+ Totals. | | 93 48 | 154
+ ----------------+----------+---------------+---------------
+ Average: 36.6 min. per ft. drilled, or 1.64 ft. drilled per hour.
+
+As a check on the average figures obtained from various sources, the
+following estimate of the cost of drilling per cubic yard was made up
+from these average figures, for comparison with the actual average cost
+on the whole work. The cost records show this to be about $2.25 per yd.,
+exclusive of power for running the drills, almost exactly what the
+following estimates give for theoretical average conditions, although no
+effort was made to have this latter compare so closely.
+
+ _Estimated Cost per Drill per Day._
+
+ Drill Runner 1 at $3.50 per day, $3.50
+ Helper 1 ” 2.00 ” ” 2.00
+ Nipper 1/5 ” 1.75 ” ” 0.35
+ Heading foreman 1/12 ” 5.00 ” ” 0.42
+ Walking boss 1/50 ” 7.50 ” ” 0.15
+ Blacksmith 1/12 ” 4.00 ” ” 0.34
+ Blacksmith helper 1/12 ” 2.00 ” ” 0.16
+ Machinist 1/12 ” 3.00 ” ” 0.25
+ Machinist helper 1/24 ” 1.75 ” ” 0.07
+ Pipe fitter and helper 1/50 ” 5.00 ” ” 0.10
+ Oil, waste, blacksmith coal, etc. 0.24
+ Drill steel, 6 in. per shift 0.20
+ -----
+ $7.78
+
+ Average number of feet drilled per cubic yard 3 to 3.5
+ Number of feet drilled per drill, per shift 10.5 to 12
+ Number of yards per drill, per shift 3.5±
+ Cost of drilling, per yard, $7.78/3.5 $2.22±
+
+In all the foregoing tables and computations, the quantities used have
+been those paid for. The quantity taken out, however, has been 10% more
+than that paid for, and 28% more than the contractor was actually
+required to take out.
+
+The specifications required that the excavation should be taken entirely
+outside of the neat line, as shown on Plate VIII of the paper by Mr.
+Jacobs, but not necessarily beyond this line, but that the contractor
+would be paid for rock out to the standard section line, which is 1 ft.
+larger on the sides and top and 6 in. deeper in the bottom than the neat
+line.
+
+A great deal of the extra quantity was due to rock falling from the
+core-wall side whenever one working face was behind the other. Blasting
+at the face behind generally loosened more or less rock on the core-wall
+side of the tunnel which was ahead, in one or two instances breaking
+entirely through, as shown in Fig. 2, Plate XXVI, the hole in the
+core-wall in this case being utilized by building a storage chamber in
+it.
+
+Table 3 gives some of the statistics of drilling in the Simplon Tunnel,
+as compared with the drilling on this work, the figures for the Simplon
+being taken from papers read before the Institution of Civil Engineers
+of Great Britain.
+
+ TABLE 3.
+ -------------------------------------------+--------------+----------
+ | |
+ | Bergen Hill. | Simplon.
+ -------------------------------------------+--------------+----------
+ Drills set up in heading, percentage of | |
+ total elapsed time | 50% | 60%
+ Actually drilling the rock, percentage of | |
+ total elapsed time | 25% | 50%
+ Average advance per round (attack) | 8.5 ft. | 3.8 ft.
+ Average time for each attack | 36 hours. | 5 hours.
+ Average advance per day of 24 hours | 5 ft. | 18 ft. †
+ Depth of holes | 10 ft. | 4.6 ft.
+ Diameter of holes | 2¾ in. | 2¾ in.
+ Linear feet drilled per hour, per drill | 2.7 | 7.0
+ Linear feet drilled per cubic yard | 5.0 | 6.0
+ Pounds of dynamite per cubic yard | 3.4 to 5.7 | 8½
+ Average depth drilled with one sharpening | 12 in. | 6½ in.
+ Total number of men per day of 24 hours* | 450 | 3,300
+ -------------------------------------------+--------------+----------
+
+ [* On Bergen Hill Tunnels, for two full working faces at the
+ Hackensack end, about 3,000 ft. in from portal (March, 1908). At
+ Simplon, two full faces and two headings, at a distance of about
+ 5,000 ft. in from the portal (January, 1900). These both include
+ lining as well as excavation. The lining of the Bergen Hill Tunnels
+ progressed about twice as fast as the excavation; it is inferred
+ that on the Simplon it progressed at about the same rate as the
+ excavation.]
+
+ [† At the Italian end, in Antigoric gneiss, which is stated to be
+ very hard rock.]
+
+The figures in Table 3 are for “heading only” in both cases, except for
+the last item (number of men), the heading in the Simplon Tunnels being
+about 60 sq. ft., as compared with the heading of Method No 4 (which has
+been used for comparison), of 210 sq. ft.
+
+
+_Mucking and Disposal._--The conditions affecting the disposal of the
+muck, after blasting, were quite different at the two ends, the grade
+descending in the direction of the loads at Weehawken and ascending at
+the Hackensack end. At the Weehawken end the mouth of the tunnels was at
+the bottom of a shaft some 80 ft. deep, Fig. 2, Plate XXII, the muck in
+the tunnel cars being hoisted by elevators to a platform at the top from
+which it was dumped into standard-gauge cars supplied by the Erie
+Railroad, as shown by Fig. 7; or later hauled to the crusher or storage
+pile, some 500 ft. distant, on the north side of Baldwin Avenue. At the
+western end, the cars were hauled directly to the surface through the
+approach cut, and the material, except that required for concrete and
+rock packing, was deposited in the embankment across the Hackensack
+Meadows, a haul of from 1,000 to 3,000 ft. beyond the portal.
+
+All disposal tracks were of 3-ft. gauge, the main running tracks being
+generally laid with 60-lb. second-hand rails, although some of lighter
+weight were used.
+
+Except for about 1,000 ft. in each tunnel at the Weehawken end, where
+the muck was loaded by hand, four steam shovels, operated by compressed
+air, were used, one at each working face. One of these was a “Marion,
+Model No. 20,” weighing 38 tons, the others were “Vulcan Little Giant,”
+of about 30 tons each. All these shovels were on standard-gauge track,
+and were moved back from 300 to 500 ft. from the working face during
+blasting.
+
+ [Illustration: Fig. 7.
+ METHOD OF EMPTYING DUMP CARS AT WEEHAWKEN SHAFT:
+ FRONT VIEW, SIDE VIEW]
+
+At Weehawken, previous to the time the shovels were installed, the muck
+was shoveled by hand into the cars from the bottom of the bench, and the
+heading muck was dumped into them from the movable platform (Jumbo)
+shown by Fig. 1, Plate XXII. There were three loading tracks at the
+face. The cars used at that time were similar to that shown by Fig. 5,
+but were about two-thirds the size and had no end door; stop-planks were
+supposed to be placed in the ends but seldom were. The loads averaged
+about ½ cu. yd. (measured in place). After the shovel was installed the
+cars shown by Fig. 5 were used, and the loads averaged nearly 1 cu. yd.
+
+The empty cars were pushed up to the shovel by hand from the storage
+track. When loaded, they were given a start with the bucket of the
+shovel, and were then allowed to coast by gravity out to the storage
+track near the shaft, where they were stopped by placing rolls of cement
+bags or burlap on the rails. After the lining was started, the loaded
+cars were stopped on the inside of the lining and only sent out over the
+single track through this latter at stated intervals, when several cars
+followed in close succession, with a long interval which permitted the
+concrete to be brought in. The empty cars were hauled back to the
+storage track near the working face by mules, one mule usually hauling
+two cars at a time.
+
+Up to the time the trap rock was reached, about 1,100 ft. from the
+shaft, the excavated material was disposed of by loading it on flat
+cars. All the trap, however, was stored to be used later for concrete
+and ballast.
+
+When the tunnels were in full working order, sixty muck cars of the type
+shown by Fig. 5, were in use, about evenly divided between the two
+tunnels. For some time the work was greatly hampered by lack of cars,
+and even with the sixty finally obtained, there were many times when
+extra cars could have been used to advantage to keep the shovel working.
+
+When mucking by hand, the mucking gangs consisted of from 15 to 20 men.
+The maximum output was 50 cu. yd., and averaged about 35 cu. yd. per
+shift; there was a great deal of trouble in keeping the gangs full, as
+labor at that time was very scarce, and the tunnels were quite wet. The
+maximum output of either of the shovels was 159 cu. yd. in one shift,
+and the best average in any month--which was between July and December,
+1907, during which time only the enlargement and bench of the Central
+Shaft headings was being taken out from the western end--was 60 cu. yd.
+per shift. As the shovels were generally idle for one shift out of
+three, the quantity actually handled averaged 90 cu. yd. per shift
+during the shifts the shovel worked. All these quantities were “measured
+in place,” and, as previously noted, would be about equal to twice as
+much measured loose in the cars.
+
+The shovels at both ends were usually worked with three crews for the
+two tunnels; two day crews, one at each shovel, and a night crew which
+was used in either tunnel as occasion required. The day crews generally
+averaged from 45 to 60 hours overtime during the month, one of them
+working during the early part of the evenings in the opposite tunnel to
+the night crew. For a short time, when the ventilation at the western
+end was very bad, four crews were worked, day and night crews in each
+tunnel; but, as a general rule, the method of working three crews was
+preferred by the men, and was less expensive for the contractor.
+
+At the Hackensack end, 4-yd., Allison, one-way, dump cars were used,
+being handled by “dinky” locomotives, of which there were three in use
+up to October, 1907, and four after that. One 15-ton Porter engine, with
+10 by 16-in. cylinders, was used outside the tunnels for handling the
+trains (from 6 to 8 cars) on the dumps and to the crusher; the other
+three, 12-ton Vulcans, 9 by 14-in., were used in the tunnels. About 30
+dump cars were in use, and of these there were generally from 3 to 6
+under repair.
+
+Generally, 4 cars were hauled out together, although 5 and occasionally
+6 were handled. The work was generally arranged so that the heavy
+mucking shift alternated in the two tunnels, the two engines being
+worked there and a single engine in the other tunnel.
+
+The tunnel engines left the cars on a track just outside the portal,
+from which they were made up into trains of from 6 to 8 cars and taken
+to the dump or crusher by the large “dinky.”
+
+The muck from the Central Shaft headings was loaded by hand into cars
+similar to that shown by Fig. 5, but smaller and having no door at the
+forward end. A double elevator took the cars to a platform about 20 ft.
+above the surface, where they were dumped by revolving platforms,
+similar to those at Weehawken, into storage bins or directly into
+wagons. The muck was all hauled away in wagons; part of it was used to
+fill some vacant lots, and part was hauled to the crusher at the Western
+Portal.
+
+The method under which the best results were obtained was that in which
+a full round was blasted every 36 hours, securing an advance of
+practically 9 ft. of full section. During the first shift of the three,
+as soon as the blasting had been completed and lights strung, the shovel
+was moved forward, and cleaned up the floor to the main pile of muck,
+the material from the blast being scattered from 150 to 300 ft. back
+from the face; during this shift, also, the drillers mucked the heading
+and set up their drills, the muckers helping to carry in the columns and
+drills. During the second shift the main pile of muck was disposed of,
+leaving not more than 2 or 3 hours’ work for the shovel on the third
+shift. This left nearly the whole of the third shift for drilling the
+lift holes.
+
+
+_Ventilation._--At Weehawken considerable difficulty was caused by fog
+and smoke accumulating in the tunnels after blasting. This was generally
+worse on days when the barometric pressure was low outside, and worse in
+the North than in the South Tunnel. A 6-ft. fan, driven by an electric
+motor, was installed in the cross-passage at Station 274, 900 ft. from
+the shaft, the headings at that time being about 300 ft. in advance of
+this point, to force the air from the South into the North Tunnel,
+drawing it in at the mouth of the South Tunnel and discharging it at the
+mouth of the North Tunnel, thus insuring a circulation in both tunnels,
+as shown in plan by Fig. 8.
+
+ [Illustration: Fig. 8.]
+
+This necessitated, of course, that the cross-passages between that in
+which the fan was placed and the mouths of the tunnels should be blocked
+tight. There was some difficulty in keeping this blocking tight, owing
+to the force of the blasting blowing out the bulkheads. The fan,
+however, did good service when it and the bulkheads were in good order.
+The compressed air discharged from the drills kept the headings fairly
+clear, as well as that part of the tunnel between the headings and the
+fan. The fan was moved ahead to the next cross-passage at Station 277
+when the work had progressed far enough, and was used there for some
+time; it was found, however, that by the time the excavation had reached
+Station 280, about 1,500 ft. from the shaft, there was practically no
+further difficulty from fog and smoke. No satisfactory explanation was
+found for this, as it would rather be expected that the ventilation and
+trouble with smoke and fumes from blasting would be worse as the
+distance increased between the mouth of the tunnel and the working face.
+One explanation was offered: That the blasting of the softer sandstone
+tended to create more and lighter dust than the heavier trap rock;
+whether or not this was so, it is a fact that there was far less trouble
+with fog and smoke after the sandstone was passed.
+
+At Hackensack, the principal cause of trouble was the smoke from the
+“dinky” locomotives. As the tunnels progressed, this gradually became
+worse, until a connection was made with the Central Shaft headings.
+A fan was installed in the cross-passage at Station 316 (700 ft. in from
+the portal), but was never worked properly. Apparently, the men, at
+least the walking bosses and foremen, had little faith in the fan as a
+means of ventilation; no real attempt was made to keep it in order or
+operate it properly, and a great deal of time and money was lost groping
+around in the smoke and fog, the density of which increased, not only
+with the state of the atmosphere, but also with the direction of the
+wind. On some days the tunnels easily cleared themselves, and on others
+the smoke was so thick that a candle held at arm’s length could not be
+seen. At this end, the South Tunnel was generally worse than the North.
+After the headings were holed through between the portal and the Central
+Shaft there was very little trouble, there being usually a strong
+up-draft through the shaft. This was so pronounced when the wind was
+blowing toward the portal, that the moisture-laden air, as it ascended
+from the mouth of the shaft, presented the appearance of a heavy
+rainstorm with the rain ascending instead of descending. When the wind
+was blowing away from the portal, that is, from the southeast, the
+effect of the shaft as a chimney was neutralized, and, consequently, the
+smoke accumulated in the tunnels. To overcome this, a large blower, with
+a fan 9 ft. in diameter, and with blades 4 ft. wide and 2 ft. 3 in.
+long, operated by a vertical 12-h.p. engine, was installed at the top of
+the shaft, and this kept the tunnels reasonably clear of smoke at all
+times. After the bench and enlargement had passed the bottom of the
+shaft, the use of the fan was abandoned, as it was found that the
+tunnels cleared themselves fairly well, probably owing to the larger
+cross-section reaching all the way to the Shaft. What little fog and
+smoke there might be did not cause enough trouble to warrant the cost of
+running the fan, which, owing to its location, required the whole time
+of a mechanic in attendance day and night.
+
+
+_Lighting._--During the earlier stages of the work, gasoline lamps and
+Kitson lights were used. The former, of the familiar banjo type, and a
+modification of this, with a section of wrought-iron pipe for the
+reservoir, were very unsatisfactory, and were out of repair and leaking
+a large proportion of the time. The Kitson lights were given only a
+short trial, but were found unsatisfactory, owing to the necessity of
+moving them frequently and having to set them up in insecure positions.
+Electric lights were installed by Mr. Bradley, on his assumption of the
+contract.
+
+The number of lamps maintained in each of the tunnels for the excavation
+was approximately as follows:
+
+ At the main working face From 8 to 10
+ On and around the shovel ” 9 to 12
+ Between the portal and the working face ” 60 to 80
+
+The cost of lighting for the whole work averaged about 15 cents per
+cu. yd., which is quite large. This was mainly due to the fact that
+current was bought from outside sources during a large part of the time
+(one-third of the yardage). Part of this current cost 5 cents per
+kw-hr., and there were fairly heavy charges for connecting the tunnel
+wiring system with the source of supply. Current bought from the Public
+Service Corporation cost from 10 to 12 cents per kw-hr. delivered at the
+mouth of the tunnel.
+
+
+_Pumping._--The quantity of water encountered during the excavation of
+the tunnels, measured somewhat roughly, was approximately as follows:
+
+ At Weehawken 74 gal. per min.
+ At Central Shaft 1 ” ” ”
+ At Hackensack 18 ” ” ”
+
+The water at the Weehawken end had to be pumped from the bottom of the
+shaft, a lift of about 90 ft., while at the Hackensack end it had to be
+pumped back from the face up grade to the portal.
+
+The cost of pumping was about $100 to $125 per month for labor for the
+whole work, besides the cost of the plant (about $1,200) and the power
+for running it.
+
+
+PROGRESS.
+
+The total time elapsed from the time of starting work at the Weehawken
+end, in May, 1905, to the completion of the excavation, in May, 1908,
+was almost exactly three years. Of this time about 40 days were lost in
+February and March, 1906, when work was stopped by the Receiver of the
+Shields Company, the total number of days actually worked being about
+940, giving an average progress of 6.26 ft. per working day in each of
+the two tunnels, which, omitting the Central Shaft headings, gives an
+average rate of progress for each working face, of 3.13 ft. per day.
+
+These 940 days include practically all the time elapsed, except Sundays
+and such few holidays as were observed. For some of this time, work was
+being carried on at only one or two points; the time, therefore,
+represents practically the total possible working time during the period
+covered.
+
+
+_Progress at Weehawken._--At Weehawken the total number of days worked
+was 763, divided as follows:
+
+186 days in timbered section, about 426 ft., an average rate of 2.3 ft.
+ per day in each tunnel;
+
+176 days in hard sandstone, about 563 ft., an average rate of 3.2 ft.
+ per day in each tunnel;
+
+112 days in hard trap, about 267 ft., an average rate of 2.4 ft. per
+ day in each tunnel;
+
+289 days in ordinary trap, about 1,316 ft., an average rate of 4.55 ft.
+ per day in each tunnel.
+
+
+_Progress at Central Shaft._--At Central Shaft the average length driven
+per day in each of the four headings is shown by Table 4.
+
+TABLE 4.
+
+ -----------+----------------+-----------------+---------------------+
+ Location. | Number of days | Total length of | Average length of |
+ | worked. | heading, in | heading driven per |
+ | | feet. | day worked, in feet.|
+ -----------+----------------+-----------------+---------------------+
+ | | | |
+ N.E. | 227 | 446 | 1.96 |
+ S.E. | 168 | 346 | 2.06 |
+ N.W. | 272 | 768 | 2.82 |
+ S.W. | 234 | 698 | 2.98 |
+ -----------+----------------+-----------------+---------------------+
+
+
+_Progress at Hackensack._--At Hackensack the total number of days worked
+on the tunnels proper, all in trap rock (omitting the cut and cover) was
+about 792, divided as shown in Table 5.
+
+ TABLE 5.
+
+ ------------------------------+----------+----------+----------+
+ |Number of | | Average |
+ Location. | days | Advance. | advance |
+ | worked. | | per day. |
+ ------------------------------+----------+----------+----------+
+ Station 323 to Central Shaft | | | |
+ headings | 492 | 1,450 | 4.5 |
+ Bench and enlargement of | 159 | { 1,150* | 7.2* |
+ Central Shaft headings | | { 906† | 5.7† |
+ Central Shaft headings to | | | |
+ Weehawken headings | 141 | 620 | 4.4 |
+ ------------------------------+----------+----------+----------+
+
+ [* Actual advance.]
+
+ [† Equivalent linear feet of full section tunnel.]
+
+The best month’s work in each location was as follows, the actual
+yardage excavated and paid for being reduced to equivalent linear feet
+of full section. The tunnels were generally taken out to full section,
+except for a small amount left in the bottom, which latter reduced the
+equivalent linear feet of full section to about 95% of the actual
+advance at the face.
+
+ _Weehawken._--
+ Feet
+ Linear per
+ feet. day.
+ Full timbered section, North Tunnel Nov., 1905, 87 = 3.0
+ Sandstone ” ” May, 1906, 109 = 3.9
+ Trap (normal) South ” July, 1907, 144 = 5.3
+
+
+ _Hackensack (All trap)._--
+ Feet
+ Linear per
+ feet. day.
+
+ Portal to Central Shaft headings,
+ South Tunnel May, 1907, 139 = 5.0
+ * Enlargement of headings,
+ ” ” Nov., 1907, 175 = 6.0
+ Central Shaft headings to Weehawken
+ headings, North Tunnel Apr., 1908, 145 = 5.2
+
+ [* The actual advance of the bench this month was 202 lin. ft.]
+
+
+_Central Shaft Headings._--During April, 1907, 122 lin. ft. of heading,
+averaging 3.8 cu. yd. per lin. ft., were taken out in the South Tunnel,
+west of the shaft. This was equal to 5.0 ft. per day for the 24 days
+worked.
+
+
+_The Best Week’s Work._--The best week’s work at either of the main
+working faces, when the full section was being excavated in trap rock,
+was 803 cu. yd., equal to 41.8 lin. ft. of full-section tunnel, or an
+average of 6.0 lin. ft. of full section per day; this was from the South
+Tunnel at Hackensack for the week ending January 11th, 1908.
+
+
+_The Best Yardage._--The largest number of yards taken out in any one
+week from one working face was 1,087, equivalent to 56.6 lin. ft. of
+full section, or an average of 8.1 lin. ft. of full section per day.
+This was bench and enlargement only (Central Shaft headings) in the
+North Tunnel, Hackensack, for the week ending October 19th, 1907.
+
+The largest yardage for the whole work in any one week was 3,238 cu. yd.
+from four working faces--two at Weehawken in full section and two at the
+Hackensack bench and enlargement (Central Shaft headings). This was
+equivalent to 168.4 lin. ft. of full-section tunnel, or an average of
+6 ft. per day from each working face.
+
+
+_The Best Month’s Work._--The best month’s work with each of the four
+methods of drilling the headings, as shown in Figs. 1, 2, 3, and 4,
+where the work was straight forward and the full section was being taken
+out, was as follows:
+
+ Method No. 1 About 90 ft. in sandstone.
+ ” No. 2 ” 100 ” in trap.
+ ” No. 3 ” 137 ” in trap.
+ ” No. 4 ” 145 ” in trap.
+
+In regard to these figures it should be noted, as stated previously,
+that the organization of the men and plant was not properly completed
+until near the time Method No. 4 was put in operation.
+
+In Fig. 9 is shown graphically the relation of the progress to the time
+elapsed in the North Tunnel, the diagram for the South Tunnel being
+almost exactly the same.
+
+
+PLANT.
+
+The plant installed by the John Shields Construction Company, and taken
+over by Mr. Bradley, was composed very largely of second-hand material,
+and eventually most of it had to be replaced. Insufficient and
+inefficient plant and delay in installation were largely responsible for
+the small progress made by the Shields Company, and Mr. Bradley’s
+endeavor to utilize this plant not only caused much delay during the
+first 8 or 10 months after he started work, but also involved large
+expense.
+
+
+_Power Plant._--At Weehawken the plant installed by the Shields Company
+consisted of three old locomotive boilers, each having a nominal
+capacity of about 125 h.p., and one Rand and one Ingersoll-Sergeant
+compressor, each of a rated capacity of about 1,250 cu. ft. of free air
+per min. compressed to 100 lb.
+
+To this Mr. Bradley added two more second-hand locomotive boilers, and
+another Rand compressor of the same type and capacity as the first. The
+theoretical steam capacity of each of the five old locomotive boilers
+was about 4,250 lb. per hour, or a total capacity of 21,250 lb. per
+hour.
+
+ [Illustration: Fig. 9.
+ PROGRESS PROFILE--NORTH TUNNEL]
+
+Theoretically, the demand on this steam was:
+
+ Pounds per hour.
+
+ Three compressors, about 5,600 lb. per hour each 16,800
+ One dynamo About 1,000
+ One 500-gal. pump ” 1,000
+ One hoisting engine for elevators ” 2,000
+ ______
+ Total 20,800
+
+Actually, there was considerable deficiency of steam when an endeavor
+was made to work the three compressors at their full capacity.
+A separate boiler was afterward installed to run the hoisting engine
+for the elevators and the pumps, thus leaving a requirement of only
+approximately 18,000 lb. of steam per hour, but even this was beyond the
+capacity of the boilers, especially as one was almost always out of
+commission.
+
+The two Rand compressors were 24 by 24 by 30-in., straight-line,
+one-stage, steam-driven, with a nominal capacity of 1,250 cu. ft. of
+free air per min. at 80 rev. per min. The Ingersoll-Sergeant was of
+similar type and capacity. Therefore, the theoretical quantity available
+was 3,750 cu. ft. of free air per min.
+
+The theoretical air requirements (as taken from manufacturers’
+catalogues) were:
+
+ Cubic feet of free
+ air per minute.
+
+ 20 Rand slugger drills (12 by 174) 2,088
+ 2 Little Giant shovels
+ (taking air two-thirds of the time) 1,100
+ -----
+ Total 3,188
+
+This estimate, based on the assumption (given in the catalogues) that
+the drills would be working about three-fifths of the time, and the
+shovels about two-thirds of the time, left apparently an ample margin
+between the full capacity of the compressors and the requirements for
+the drills; as a matter of fact, however, it was seldom that more than
+80 lb. of air was available, and the pressure often dropped to 60 or 50
+lb. at the compressors. During the time this plant was in use the
+greatest distance to the drills was about 1,500 ft.
+
+As this plant proved to be entirely inadequate to the demands, an
+arrangement was made with the O’Rourke Construction Company on August
+17th, 1906, whereby they agreed to supplement the air supply by 1,000
+cu. ft. of free air per min. at 100 lb. pressure. This arrangement was
+not altogether satisfactory, and finally (on December 5th, 1906) an
+arrangement was made with the same company to supply air up to 4,000 cu.
+ft. of free air per min. at 100 lb., and the old plant was shut down.
+
+The new plant had been in use previously in the construction of the
+River Tunnels. The air from it was compressed to 40 lb. by low-pressure
+machines, one being used all the time and two when necessary. These
+machines were built by the Ingersoll-Sergeant Company, the engines being
+of the Corliss duplex type, cross-compound steam, with simple duplex air
+cylinders, each compressor having a capacity of nearly 4,000 cu. ft.
+of free air per min. This air, at 40 lb., was delivered to an
+Ingersoll-Sergeant high-pressure machine, having Corliss cross-compound
+engines, 14 by 26 by 36-in., with air cylinders of the piston inlet
+type, 13¼ by 36-in., which compressed it to 100 lb. The capacity of this
+latter machine, taking air at normal pressure, is 920 cu. ft. of free
+air per min. working at 85 rev. per min.; by taking the air at 40 lb.,
+and working at a somewhat higher speed, this machine alone supplied all
+the air used at the Weehawken end (approximately 4,000 ft.) from
+December, 1906, to November, 1907, and, with very few exceptions, the
+pressure was steadily maintained at from 90 to 100 lb., there being no
+break-down of any kind.
+
+At Hackensack the plant taken over by Mr. Bradley consisted of six old
+locomotive boilers and four Rand compressors, all of the same type as
+those at Weehawken. To this he added two second-hand marine boilers,
+each of a stated capacity of about 350 h.p., and two more Rand
+compressors of the same type and capacity as the others, making the
+total theoretical steam power available approximately 1,450 h.p., with a
+compressor capacity of approximately 7,500 cu. ft. of free air per min.,
+equal to about 1,500 h.p., allowing for 15% of loss.
+
+Nowhere near the theoretical steam power was ever developed from the
+boilers. The tubes of the old locomotive boilers were filled with mud in
+many cases, and were always leaking. The marine boilers were not
+properly installed to give the best results, and it was seldom possible
+to work more than four compressors at once, or to keep the air pressure
+at the power-house much greater than from 70 to 80 lb. at any time.
+
+This plant had been built by the Shields Company on the meadows
+alongside the Erie and New York, Susquehanna and Western Railroads, and
+the foundations were not made sufficiently strong to resist the effect
+of the vibration caused by the passing trains. It was impossible to keep
+the steam connections tight, and there was not only the loss of steam
+due to leaky joints, but positive danger of one of the main steam lines
+breaking entirely. After attempting to operate this plant for nearly 5
+months, Mr. Bradley determined to abandon the site and the boilers, and
+build a new plant, farther back from the railroad, on solid ground, in
+such a position that a spur track could be built to a coal trestle in
+front of the boilers.
+
+Two pairs of Stirling boilers, with a total capacity of 2,000 h.p., were
+installed. As a rule, at times of maximum demand, three of the boilers
+were in use; after the Central Shaft was stopped, two were generally
+sufficient, until, toward the latter part of the excavation, the losses
+in the transmission of the air made it necessary to keep three going.
+
+Eight compressors (the six old ones with two brought from Weehawken),
+were installed in the new power-house. All were of the same type,
+namely, Rand, straight-line, steam-driven, 24 by 24 by 30-in., each with
+a nominal capacity of 1,250 cu. ft. of free air per min. Seven of these
+were generally worked to their full capacity in order to keep up the
+necessary supply of air.
+
+The maximum requirements of air at this end were primarily estimated as
+follows:
+
+ Central Shaft, four headings 24 drills.
+ Hackensack, two working faces 20 drills.
+ ----------
+ Total 44 drills.
+
+ Cubic feet of free
+ air per minute.
+
+ 44 Slugger drills (25 by 174) require 4,350
+ 2 Steam shovels 1,600
+ Pumps and machine-shop, say 1,000
+ 4 Hoisting engines, placing concrete 2,000
+ 4 Derricks 2,000
+ ------
+ Total 10,950
+
+The theoretical capacity of the whole eight compressors was:
+
+ 1250 × 8 = 10,000 cu. ft. of free air per min.
+
+It was considered that not more than two-thirds of the above equipment
+would be working at the same time; the actual requirement, therefore,
+was taken at about 8,000 cu. ft. of free air per min., thus leaving a
+margin of one spare compressor.
+
+As actually worked out, there were probably never more than eight drills
+working at any one time at the Central Shaft, and this work was entirely
+suspended in June, 1907, before there was any demand for power in
+connection with the tunnel lining. The heaviest actual requirement,
+therefore, was approximately as follows:
+
+ (_A_) _Previous to June 25th, 1907:_
+
+ Cubic feet of free
+ air per minute.
+
+ 40 Drills (22 by 174) 3,828
+ 2 Shovels 1,600
+ Pumps and machine-shop, say 1,000
+ 2 Derricks 1,000
+ -----
+ Total 7,428
+
+ (_B_) _After November, 1907_ (_after completion of enlargement of
+ Central Shaft headings_):
+ Cubic feet of free
+ air per minute.
+
+ 32 Drills (17 by 174) 2,958
+ 2 Shovels 1,600
+ Pumps, etc 1,000
+ 3 Hoisting engines on concrete,
+ each working one-third time 500
+ 2 Derricks 1,000
+ -----
+ Total 7,058
+
+The average number of drillers per shift was about 25 at the two main
+working faces. There were also from 5 to 10 drills trimming and cleaning
+up for concrete, say an average of 7, making 32 in all.
+
+After November 1st, it actually required three boilers under steam all
+the time, and not less than seven compressors running at full capacity,
+to keep the air at proper pressure, the theoretical capacity of the
+compressors being 8,750 cu. ft. of free air per min., as against 7,000
+to 7,400 cu. ft., the theoretical maximum requirement.
+
+Some of this deficiency was due to losses in transmission, part also was
+due to the fact that the actual was probably considerably below the
+theoretical capacity of the compressors.
+
+
+ACCIDENTS.
+
+Two accidents occurred to the powder magazines, the causes of which were
+never absolutely determined. The first occurred on January 10th, 1907,
+when the dynamite burned up without exploding. The second accident was
+on March 3d, 1907, when an explosion occurred which damaged property
+over a very large area, but did not involve any serious injury to
+persons, only one man being slightly hurt.
+
+The only serious blasting accident in the tunnels occurred on January
+26th, 1908, and was due to a premature blast, the cause for which could
+not be ascertained.
+
+
+_Contractor’s Organization._--The work was in general charge of a
+superintendent, and, during the time it was being carried on at both
+ends, an assistant superintendent had charge at night. At each end there
+was a day and a night walking boss, who had general supervision of the
+men in the tunnels, the day walking boss being the superior, and
+responsible for the general conduct of the work at his end, both day and
+night. Two 10-hour shifts were worked, thirteen shifts every two weeks,
+no work being done on alternate Sundays and Sunday nights. With the
+exception of the walking bosses and the master mechanic, all the men
+changed from the day to the night shift every two weeks.
+
+The organization was approximately as follows, for each shift:
+
+ _General_--_Both Tunnels._
+
+ 1 Master mechanic (days only),
+ 1 Machinist,
+ 1 Engine runner,
+ 2 Firemen,
+ 2 Oilers,
+ 1 Electrician and helper,
+ 1 Drill machinist and helper,
+ 3 Blacksmiths and helpers,
+ 1 Powderman,
+ 1 Walking boss,
+ 4 Locomotive engine runners,
+ 4 Brakemen,
+ 1 Switchman,
+ 1 Foreman on dump,
+ 6 Men on dump,
+ 1 Foreman on track,
+ 6 Men on track.
+
+ _In Each Tunnel._
+
+ _Drilling and Blasting._
+ 1 Foreman,
+ 12 Drillers,
+ 12 Helpers,
+ 1 Nipper,
+ 1 Pipe-fitter.
+ _Mucking._
+ 1 Shovel engineer,
+ 1 Cranesman,
+ 1 Muck boss,
+ 12 Muckers.
+
+
+RECORDS.
+
+The records of the work have been based largely on the reports of the
+day and night inspectors, which were made out on regular forms.
+
+A daily report card was made out each morning and forwarded to the
+office of the chief engineer. It covered the work done for the previous
+24 hours, up to 6 o’clock each morning.
+
+A telephone report was made to the resident engineer by the inspectors
+each day at 8.30 A.M., giving the conditions, number of men, etc., at
+the opening of the day’s work.
+
+A daily progress profile, on 10 by 10 to the inch cross-section paper,
+covering the whole length of the tunnels, was kept in the office of the
+resident engineer. This was mounted in sections, on a piece of
+composition board, and hung on the wall for convenient reference. The
+information, showing the progress up to 6 o’clock each morning, was
+shown on the report of the night inspector, and was plotted on this
+profile at 7 o’clock each morning. The plotting was left in pencil, and
+each month’s work was colored in. A progress profile was taken by the
+men of the alignment corps each Saturday morning and plotted by them,
+alternate weeks being in red and blue ink on the same profile.
+
+A chart showing the number of drills working, time worked, blasting
+periods, etc. (Plate XXIII), was plotted each morning and was extremely
+useful, not only in keeping in touch with the work, but in compiling
+many of the statistics used in the preparation of this paper. These
+cross-section sheets were ruled 12 by 12 to the inch, thus giving one
+space per hour horizontally. In the top vertical space are shown the
+heading drills, their time of stopping and starting, and their number,
+each heavy line representing one drill. In the next space below are
+shown the drills on the bench, lift holes, etc.
+
+The blasting time is shown by the portion hatched (shown in red on the
+original), which covers the whole vertical space when a complete round
+of both heading and bench is blasted, and only part, top or bottom, as
+the case might be, if only one or the other. The number of drillers and
+muckers at the main working face is shown, and below that (in red ink on
+the original) the number of cubic yards handled each shift. The time the
+shovel is working is shown by the heavy line filling a whole space; and
+the air pressure, platted from the recording gauge charts, is shown in
+the space below.
+
+A combination daily and weekly report, showing the total number of men
+working on each section, and the number of cubic yards excavated, was
+entered every day and kept on a filing board in the office of the
+resident engineer, and a copy was sent to the main office at the end of
+the week, with such notes on the back as might be necessary, or of
+interest.
+
+A report was made out weekly and sent to the contractor’s
+superintendent, showing any deviations from grade, any tight places, and
+the station of bench and headings.
+
+A monthly report was made to the chief engineer, giving detailed
+statistics of the amount of work done, etc., plant installed, and short
+notes of any matter of interest affecting the work in any way.
+
+
+TUNNEL LINING.
+
+_Preliminary Considerations._--For the placing of the concrete lining, a
+sub-contract was given to Messrs. King, Rice and Ganey, by Mr. Bradley,
+which provided substantially that all materials should be supplied by
+him, and delivered to the sub-contractors at track level, at or near the
+point in the tunnel at which they were to be placed, and that he would
+supply light and power; the sub-contractors were to supply the plant,
+forms, and labor necessary for placing the concrete and water-proofing,
+building the conduit lines, manholes, etc., etc., to complete the
+lining, the general form of which is shown on Plate VIII of the paper by
+Mr. Jacobs, and in Fig. 10. The latter also shows the different sections
+into which the lining was divided for purposes of construction, and the
+nomenclature adopted for each. It may be noted, incidentally, that the
+cubic contents of the lining per linear foot of tunnel is almost exactly
+half the quantity excavated, out to the standard section lines, and as
+there was some excavation outside of these lines, all of which had to be
+replaced, the actual quantity of material which had to be brought back
+into the tunnel was quite a little more than half the quantity taken
+out. It will be evident, therefore, that the question of transportation
+was an important one.
+
+ [Illustration: Fig. 10.
+ SKETCH SHOWING DIVISION OF LINING FOR PURPOSES OF CONSTRUCTION,
+ AND NAMES OF SECTIONS]
+
+An essential part of the agreement with the sub-contractors provided
+that the operations incident to the placing of the lining should be
+carried on so as to provide at all times space for a single track of
+3-ft. gauge, running through the work, and the necessary clearance for
+the locomotives and cars used in hauling out the muck. A clearance
+diagram of one of the “dinkys” used in the tunnels, and its relation to
+the forms used, is shown by Fig. 12 and also by Fig. 16, the 4-yd.
+Allison cars, used for handling the muck, taking practically the same
+width, although they were not quite as high. This requirement and the
+limited space available must be kept in mind in considering the design
+finally adopted for the forms and plant required in placing the lining.
+It should also be kept in mind that, with the rolling stock used, there
+was only room for a single track through that part of the tunnel where
+any concrete had been built. As the concrete progressed, therefore, the
+length of single track was necessarily lengthened, and the problem of
+transportation was made increasingly difficult.
+
+In working out a design for the bench-wall forms, another highly
+important and controlling factor, which had to be considered, was the
+arrangement of the conduit lines, as shown in the general
+cross-section.[2]
+
+ [Footnote 2: Plate VIII of the paper by Mr. Jacobs.]
+
+The quantities of the various materials in the lining, per linear foot
+of tunnel, were as follows:
+
+ Concrete 7.64 cu. yd.
+ Rock packing: Paid for 1.48 cu. yd.
+ Outside standard section line 1.74 ” ”
+ ------------ 3.22 ” ”
+ Iron and steel 44.2 lb.
+ Vitrified conduits 84.0 duct ft.
+ Water-proofing 13.0 sq. ft.
+ Flags 3.3 ” ”
+
+
+_General Methods._--The lining was started at both ends of the tunnels
+before the headings were finally holed through, so that there was
+practically a separate organization at each end, each in charge of one
+of the members of the firm. The work at the Weehawken end was started
+first, and the plant and scheme of working adopted there was thoroughly
+tried out before the plant for the western end was built, consequently,
+the latter was somewhat more efficient, being designed in the light of
+the experience gained at the Weehawken end.
+
+The general sequence of the plan first adopted in placing the concrete
+is shown by Fig. 10. The concrete was first placed in the foundations up
+to the elevation of the bottom of the conduit bines, this work, of
+course, being kept well in advance; next followed, in the order named,
+the sand-walls, water-proofing, conduits, bench-walls, and finally the
+arch. The foundation was built in any convenient lengths, multiples of
+16 ft., the length of one section of form, the sand-walls in lengths of
+from 25 to 35 ft., the bench-walls in 25-ft. lengths, and the arch in
+10-ft. lengths. Concrete was placed during the day shift only, the forms
+being moved partly at night, and partly on the alternate days when
+concrete was not being placed in them.
+
+Five gangs were organized at each end, the first placed concrete in the
+foundations in both tunnels, as the excavation was ready. In each tunnel
+there was a gang which built sand-wall one day and bench-wall the next,
+the two tunnels alternating so that only one bench-wall was built each
+day, and finally a gang in each tunnel building arches, a 10-ft. section
+being completed each day. During the night shift, the arch forms and
+travelers were moved, and all other forms, etc., were made ready for the
+concrete to be placed the following day. Some of the conduit laying was
+done by the night shift, but part of it was necessarily done during the
+day, as the concrete was built up. A small gang was kept busy in both
+tunnels, during the day shift, laying conduits and water-proofing. The
+latter two operations were generally performed by the same gang.
+
+This organization, of course, required considerable regularity in the
+work, and this was finally attained, but at the beginning many sections
+were often not finished on time, thus creating considerable confusion.
+The progress possible with this organization (finally maintained with
+great regularity) was 75 ft. of bench-wall and 60 ft. of arch per week
+at each of the two working faces in each tunnel. This allowed the
+bench-wall to gain considerably on the arch, and therefore at a suitable
+point, as shown on the progress diagram, Fig. 9, a third pair of arches
+was started, one in each tunnel, increasing the progress on the arches
+to 180 ft. per week in each tunnel.
+
+
+_Mixing and Transportation._--All the concrete used on this section was
+mixed in Hains mixers, one being at each end. At the Weehawken shaft the
+mixer was installed in the framework supporting the head-house and
+elevators; and storage bins were arranged above, as shown by Fig. 11,
+_A_, the whole structure being somewhat strengthened to allow this to be
+done. At the western end the mixer was placed immediately under the bins
+of the stone crusher, as shown by Fig. 11, _B_, the track below being
+connected directly with the tunnels. The stone bin under the screen of
+the crusher plant at the Hackensack end was divided into three parts,
+the center being filled with sand by a derrick having a clam-shell
+bucket, the other two with stone directly from the screen above.
+
+This type of mixer proved very efficient on this work. The largest
+number of full batches (0.8 cu. yd.) mixed in one plant per hour was
+about 35; the largest number per day of 10 hours was about 240; but the
+apparatus was never worked to its full capacity, the quantity of
+concrete which it was possible to use being limited by other
+considerations.
+
+ [Illustration: Fig. 11.
+ _A_ CROSS-SECTION OF HAINS MIXER INSTALLATION, AT WEEHAWKEN SHAFT
+ _B_ CROSS-SECTION OF HAINS MIXER INSTALLATION,
+ STONE AND SAND BINS ABOVE AND SCREEN OF CRUSHER, AT HACKENSACK
+ PORTAL]
+
+The concrete for the foundations was hauled in steel, =V=-shaped,
+dumping cars holding about 1 cu. yd., and the concrete for the
+bench-walls and arches in Stuebner, 1-yd., bottom-dumping buckets placed
+on small flat cars, as shown by Fig. 1, Plate XXIV. Rock packing was
+handled in Allison 4-yd. cars and also in the cars shown by Fig. 5,
+as well as in the Stuebner buckets, the latter, however, being most
+generally used. Mules were used for a short time at the Weehawken end to
+haul the concrete in, but proved entirely inadequate to haul the loaded
+cars up the 1.3% grade, and locomotives were substituted after the
+headings were holed through. At the western end the cars were allowed to
+coast in, and, up to the time the headings were holed through, were
+hauled back by mules; after that they were pushed out by a locomotive
+which had gone in ahead of them. As a rule, from 8 to 10 cars of
+concrete and rock packing were sent in, one after the other, in proper
+order, a boy riding on each car and stopping it at the proper place; all
+these cars were pushed out together when empty.
+
+ [Illustration: Plate XXIV.
+ Fig. 1: K 131. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, North Tunnel. Rear view of conveyor for
+ concrete, showing method of hoisting bucket from car on track in
+ hopper over belt. June 7, 07.
+ Fig. 2: K 130. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, South Tunnel. View showing waterproofing
+ (extreme left) portion of completed sand wall, sand wall forms,
+ traveller and end of conveyor overhead. July 22, 07.
+ Fig. 3: K 148. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken. View showing method of placing concrete in
+ forms. Hoisting apparatus and bucket in background. Sept. 24, 07.
+ Fig. 4: K 154. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, North Tunnel. Method of placing concrete
+ in bench walls. Top of waterproofing suspended from top of sandwall.
+ Oct. 21, 07.]
+
+During the time the excavation was being carried on simultaneously with
+the lining at the Weehawken end, the rock packing was loaded at the
+working face and sent out to the point where it was to be used; after
+that the rock packing was sent in from outside from the reserve pile on
+the north side of Baldwin Avenue.
+
+At the western end the larger part of the rock packing was sent in from
+outside, but occasionally, during the time the excavation was going on,
+the cars from the heading were stopped at convenient points, generally
+under the gantries, where the lining was being placed, and whatever
+stone could be utilized was sorted from the top and passed up to the
+platforms above.
+
+After the headings were holed through, there was considerable difficulty
+at times in getting a sufficient supply of concrete and rock packing
+into the tunnel at the time it was required, and while undoubtedly the
+transportation facilities may have had some influence in this, the
+principal trouble lay in the difficulty of securing a sufficient supply
+of proper stone for rock packing, and for the crusher.
+
+While the excavation was progressing, the cars of muck, as they came
+from the headings, were taken directly to the crusher and dumped into
+it, the proportion of fine material being fairly constant and the supply
+regular. At this time, also, a portion of the rock not required at the
+crusher was dumped along the edge of the bank on the south side of the
+approach, the larger stones rolling to the bottom where they were easily
+available to be loaded into cars for rock packing, being entirely free
+from the fine material; as this stone at the bottom of the bank was used
+up, the supply was renewed, the rock suitable for rock packing being
+automatically separated from the fine material as it rolled to the foot
+of the slope.
+
+After the excavation was completed, however, it was necessary to go into
+the bulk of the storage piles to get material for the crusher and for
+rock packing, and then the difficulties were materially increased by the
+large quantity of fine material encountered, the proportion remaining
+after the rock packing had been sorted out being too large to send
+through the crusher. It was not only the handling over of this fine
+material which caused delay, but the difficulty of disposing of it. On
+rainy days the trouble was increased by the difficulty of getting men to
+work in the open.
+
+The delays due to transportation were usually caused by derailments,
+which were more numerous than they should have been, and were due to the
+condition of the rolling stock rather than to that of the track. These
+delays, especially when they occurred in the early part of the day,
+greatly increased the cost, by necessitating over-time work; a delay of
+1 hour in the forenoon generally meant 2 hours’ work after 6 o’clock to
+finish the day’s work.
+
+The average number of cars handled (round trips of 1 car) during a day
+(two 10-hour shifts) at the Hackensack end during January, 1908, when
+the excavation and lining were in full swing, was about 125 cars of muck
+and 200 cars of lining material, the former being hauled by locomotives
+and the latter by mules.
+
+
+_Methods of Handling Concrete in the Tunnels._--The concrete for the
+floor, ditches, and foundations, was brought into the tunnel in
+=V=-shaped steel, dumping cars, and dumped as near as possible to the
+place it was to occupy.
+
+The concrete for the arches and bench-walls was loaded at the mixers
+into 1-yd., Stuebner, bottom-dumping buckets which just held a 4-bag
+batch. These buckets were placed on small flat cars, hauled into the
+tunnel, placed beneath the traveling gantry, as shown by Fig. 1, Plate
+XXIV, and hoisted to the platform above.
+
+These traveling gantries, the details of which are shown by Fig. 12,
+consisted essentially of platforms at each end of which an =A=-frame was
+erected; the latter supported at their apexes two =I=-beams, from the
+lower flanges of which was suspended a traveling block, shown at _A_,
+Fig. 12, and through which the hoisting rope was rigged. The buckets
+were hoisted through an opening in the platform and then moved along to
+where they could be dumped. The platforms were supported on wheels
+traveling on rails laid on the concrete of the foundation (for the
+bench-wall gantries) or on top of the bench-wall (for the arch
+gantries).
+
+Each of the first two of these traveling gantries used was equipped with
+a belt conveyor working on a cantilever arm, as shown by Figs. 3 and 4,
+Plate XXI, and Figs. 1 and 2, Plate XXIV. In using these belt conveyors,
+the concrete was dumped from the Stuebner bucket into a hopper, Fig. 1,
+Plate XXIV, with an adjustable slot in the bottom, under which the belt
+ran.
+
+ [Illustration: Fig. 12. [Full Page]
+ DETAILS OF TRAVELING GANTRY USED IN THE CONSTRUCTION OF THE TUNNEL
+ LINING:
+ SECTIONAL ELEVATION
+ CROSS-SECTION
+ A. DETAIL OF TRAVELING BLOCK
+ B. DETAIL OF TOP SHEAVE
+ C. DETAIL OF LOWER SHEAVE.]
+
+It was the original intention, in designing the conveyor, that the end
+of the cantilever arm should be swung from one side of the tunnel to the
+other, and that the traveler should be moved backward or forward, as
+might be required, and thus deliver the concrete from the end of the
+belt directly over the place in which it was to be deposited in the
+bench-walls. As a matter of fact, it was found impractical in operation
+to move the gantry readily, owing to its great weight, which was
+supported on only four ordinary car wheels and their bearings, and it
+was found more convenient to leave the arm in one position near the
+center, letting the concrete drop on the platform above the bench- or
+sand-wall forms, whence it could be shoveled into place, than to attempt
+to move it as had been intended. Both of these difficulties might
+possibly have been overcome by modifications in the design of the gantry
+and conveyor, had this method of handling the concrete seemed otherwise
+desirable.
+
+The principal difficulty with its use, however, was the inability to
+take care of more than one batch of concrete at a time. When one batch
+had been dumped into the hopper, a second could not be disposed of until
+the first had nearly all run through on the belt, and this took from 7
+to 20 min., varying with the consistency of the concrete, etc. In a few
+instances, where there happened to be some fairly dry batches, the
+concrete could not be started through the slot at all, and had to be
+shoveled out of the hopper. On the other hand, it is stated that some
+batches, under favorable conditions, passed through in about 2 min., but
+this was quite exceptional, and the operation was irregular and
+uncertain.
+
+Before the final method of handling the concrete was adopted, a trial
+was made of two forms of cars and buckets, to be used on the top
+platform, as shown by Figs. 3 and 4, and Plate XXIV. In the method shown
+by Fig. 3, Plate XXIV, the concrete was hoisted in the regular Stuebner
+buckets, one of which can be seen suspended in the background of this
+photograph, and dumped into the car shown, which was mounted so that it
+could be revolved in a horizontal plane. It was intended to move this
+car on the tracks to the point at which the concrete was required, and
+dump it directly through a chute into the bench-walls. This car was
+abandoned, as there was a great deal of difficulty in turning it when it
+was loaded, and in several instances it had to be dumped straight ahead
+in the middle of the platform and the concrete shoveled into the forms.
+This method was also objectionable when the bucket was dumped, inasmuch
+as the force of the impact of a whole batch of concrete dumped from such
+a height into the forms, not only tended to throw the conduits out of
+line, and to break them, but also caused considerable strain on the
+forms.
+
+The bucket shown by Fig. 4, Plate XXIV, was next tried. It had a
+slanting bottom and a door opening at the side. It was filled at the
+mixer, came into the tunnel on a small flat car, and was hoisted and
+placed on a similar car on top, as shown. This bucket was not
+successful, as its great weight made it difficult to handle, and it
+generally required a man to shovel the concrete out, which latter, of
+course, had been pretty well compacted in the bottom of the bucket by
+its trip from the mixer. All these cars were hauled backward and forward
+on the top platform by a rope running to the winch on the hoisting
+engine on the traveling gantry.
+
+Aside from the fact that neither type was a success, neither of these
+schemes was much improvement over the belt, inasmuch as only one batch
+could be handled at a time, owing to the necessity of using the engine
+to haul the cars back and forth on the platform. The final solution was
+found in the use of the traveling gantry, shown by Fig. 12 and Fig. 1,
+Plate XXVI, the latter being one of the arch gantries. The gantry used
+for the bench- and sand-walls was supported on framed bents on wheels
+running on rails laid on the foundation; that for the arch was the same,
+except that the high-framed bent was dispensed with, the side-sills
+resting directly on the journals of wheels traveling on rails on top of
+the finished bench-wall.
+
+These gantries were used only as a means of hoisting the buckets and
+moving them along to where they could be dumped directly on the
+platform, whence the concrete was shoveled into wheel-barrows, which
+could be dumped directly into the bench-walls; or, in the case of the
+arches, shoveled from the platform of the gantry to the intermediate
+platform on the arch ribs, and thence directly into the arch. This use
+of wheel-barrows, though apparently a somewhat crude method and a
+retrogression from the use of the belt conveyor, proved very successful,
+and really involved no more labor than did the conveyors, although this
+might not have been the case had these latter worked as they were
+originally designed to.
+
+The method finally adopted allowed as many as four buckets to be dumped
+on the platform on one end of the arch gantry at one time, and eight on
+one end of that used for the bench-walls, the workmen handling about
+three of these latter into the forms by the time the last of the eight
+was dumped. It required about 1½ min. to place a car under the gantry,
+hoist the bucket, dump, close it, and return it to the car below.
+
+Rock packing was stored at the other end of the platform, for use as
+required, when it was not handled directly from the end nearest the
+work. This method allowed the concrete and other materials to be brought
+in in trains at infrequent intervals, and provided a sufficient supply
+of material on hand so that the men handling it on top could be kept
+steadily at work.
+
+Each hoisting engine on these gantries had 7 by 10-in. cylinders, and a
+double drum; some of them were Lamberts and some Mundys, operated by
+compressed air.
+
+
+_Ditches, Floor and Foundations._--The first method of building the
+foundation was that shown by Fig. 13, _A_; no attempt was then made to
+build the ditch, or floor, the intention being to leave these until the
+completion of the remainder of the lining. In building the bench-wall on
+this foundation, however, it was found difficult to secure the bottom of
+the forms properly (Fig. 2, Plate XXV), so as to prevent any give, as
+the material under the track was not solid enough to brace against. It
+was decided, therefore, to build the whole of the ditch (see Fig. 13,
+_B_) so that the bottom of the forms could be braced against the solid
+concrete. At the beginning of the work, the face of the bench-wall was
+built up to the level of the bottom of the conduits with the foundation;
+if, therefore, in placing the concrete above this level, extreme care
+were not taken to get a tight fit between the bench-wall form and the
+lower face, and then to hold it rigidly in place, the result was a
+rather unsightly horizontal joint high enough to be plainly visible. The
+position of this joint may be seen in Fig. 2, Plate XXV, which shows the
+first section of bench-wall built. Several subsequent sections showed an
+overhang above this joint, amounting in one or two cases to as much as ½
+in., due to the fact that the bench-wall form moved or did not fit
+tightly. This defect was obviated by building the foundations with an
+offset on the face, shown by Fig. 13, _B_, so that the joint came at the
+level of the top of the flagging over the ditches, and therefore was
+almost entirely concealed; at the same time this allowed a sufficient
+surface, on the plane of the face of the bench-wall, against which the
+bench-wall forms could be braced and lined up.
+
+ [Illustration: Fig. 13.
+ PLAN SHOWING VARIOUS METHODS OF BUILDING FLOOR AND FOUNDATION,
+ AND DETAILS OF FORMS]
+
+The ditch forms were set very carefully to line and grade by the
+alignment corps, as this formed the starting point of all the rest of
+the work, the only other thing which was necessary was to give a level
+at the front end of the bench-wall form, after it was set, for the
+elevation of the top of the bench, and to check up the stations of the
+ends of the sections occasionally to see that they were at the even
+25-ft. points (that is +08, +33, +58, and +83).
+
+After a short length had been built with the ditches only, it was
+thought desirable to try and put in the floor as well, so that the whole
+of the concrete would be put in place as the lining advanced, and leave
+less cleaning up to be done over the end of a single track, in the
+restricted spaces between the bench-walls. Fig. 13, _C_, shows the
+method finally adopted. In this may be seen the three stages in which it
+was put in, the details of the ditch forms being shown by Fig. 13, _D_.
+
+In that part of the tunnel where sand-walls were built, a hollow tile
+drain was built into the foundation, as shown in Fig. 13, _A_ and _B_,
+along the foot of the water-proofing and connected at intervals with the
+drains by 4-in. cast-iron pipes. When the sand-walls and water-proofing
+were not built, however, the concrete of the foundations was sloped from
+the neat line back to the rock, as shown by Fig. 13, _C_3, so that in
+case any water found its way down through the rock packing, its tendency
+would be to flow back against the rock, or to follow the low part of
+this concrete to 4-in. cast-iron pipes leading to the side ditches,
+rather than to find its way through the joint between the foundation and
+the bench-wall and so into the lower duct lines.
+
+
+_Sand-Walls._--The sand-wall forms first used are shown in Fig. 2, Plate
+XXIV, with a section of the finished sand-wall. As this work was only
+intended to give a comparatively smooth surface against which to place
+the water-proofing, no particular care was taken with the surface,
+except to avoid sharp projections which might cut through the felt and
+pitch used for this purpose. A rather porous concrete (with all the rock
+which could be safely embedded in it and have the wall stand) was used,
+so that it would not act as a dam, but rather tend to allow the water to
+find its way to the bottom of the tunnel, and so into the drains.
+
+The traveling gantry for placing the concrete in the sand-walls, as
+first designed, with the belt conveyor, could of course only deliver the
+concrete at one end. Before setting the forms for a new section, it was
+necessary, therefore, to move the gantry ahead, before the cross-bracing
+between the tops of the forms, which also held the top platform, could
+be placed in position. Fig. 2, Plate XXIV, shows the end of the conveyor
+over the top of the cross-braces. In order to hold the bottom of these
+forms, small wooden blocks were embedded in the foundation concrete,
+against which they could be wedged, as shown by Fig. 13, _A_; these
+blocks were cut out after the sand-wall had been built.
+
+After the forms had been filled, the conveyor could not be moved back to
+the bench-wall until the concrete had set sufficiently so that these
+cross-braces could be removed, and, on account of the overhang at the
+top, the set had to be fairly good in order to prevent this overhang
+from breaking off. This arrangement, therefore, for placing the concrete
+was found to be impractical, if the proposed schedule of a section of
+bench-wall and a section of sand-wall to be built on alternate days, was
+to be carried out. In a few instances, where the sand-wall was finished
+fairly early in the afternoon, the forms were released next morning, and
+the conveyor was moved back, but, even then, 2 or 3 hours at least were
+lost at the beginning of the shift. The conveyor, however, was
+abandoned, for the reasons previously given, and the traveling gantry
+was rearranged to allow concrete to be delivered at either end; it was
+then only necessary to move it backward and forward between the bench-
+and sand-wall forms instead of through these forms. This permitted the
+construction of the much more substantial type of forms shown by Fig.
+14.
+
+After being moved ahead on the track on top of the foundation, the form
+was first blocked up to grade, and then adjusted to line by the screws
+and slotted cleats shown at _B_, Fig. 14, after which it was secured by
+the braces from the ditches, as shown. The face lagging was placed in
+separate pieces and held against the uprights by lightly nailing every
+third or fourth piece; the whole was removed each time the form was
+moved, and built up again as the concrete was placed.
+
+Considerable care was taken to slope the top of the sand-wall back
+toward the rock, as shown by Fig. 14, and to allow free drainage along
+the top (which ran parallel to the grade of the tunnel) to the 4-in.
+cast-iron drain pipes which carried the water from the rock packing
+above the arch to the drains beneath the track.
+
+Sand-walls were built for a length of about 1,100 ft. in each tunnel at
+the Weehawken end, and about 700 ft. in each tunnel at the western end,
+the remainder of the work, with the exception of a few short stretches,
+not being considered wet enough to require water-proofing.
+
+
+ [Illustration: Fig. 14.
+ TRAVELING FORM FOR BUILDING SAND-WALL;
+ DETAIL SHOWING METHOD OF HANGING WATER-PROOFING FROM TOP OF SAND-WALL]
+
+_Conduits._--The arrangement of the conduit lines is shown in the
+general cross-section.[3] On the core-wall side there are 48 lines for
+telegraph and telephone cables, built of 4-way multiple conduit, each
+piece of which is 3 ft. long and about 10 in. square outside. On the
+other side there are the high- and low-tension lines, built of single
+conduit 18 in. long and a little more than 5 in. square outside.
+Manholes or splicing chambers are built every 400 ft., and are about
+8 ft. long and 4 ft. wide. General views of the conduits as built are
+shown in Fig. 4, Plate XXV, which shows all the lines in one tunnel, and
+in Fig. 1, Plate XXV, which shows the telegraph and telephone lines,
+with the expanding mandrels used in laying them.
+
+ [Footnote 3: Plate VIII in the paper by Mr. Jacobs.]
+
+ [Illustration: Plate XXV.
+ Fig. 1: K 173. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) Hackensack Portal and Approach. Telephone and Telegraph
+ ducts and mandrels. Nov. 20, 08.
+ Fig. 2: K 125. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, North Tunnel. View showing general
+ construction of tunnel lining forms, and clearance to allow disposal
+ of excavated material. June 17, 07.
+ Fig. 3: K 156. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken Shaft, South Tunnel. North side looking East,
+ showing method of placing waterproofing. Oct. 22, 07.
+ Fig. 4: K 147. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Weehawken. General view showing center and first section of
+ arch and completed lining, North Tunnel. Sept. 24, 07.]
+
+In attempting to plan the work of placing the lining, two methods of
+building the bench-wall were considered. One was to build the wall in
+longitudinal sections, each section separated by a line of ducts; and
+the other was to attempt to build the wall in the manner called for by
+the specifications, which required the concrete to be carried up in
+layers as the conduits were laid. In this latter method, it was proposed
+to bond the concrete together with the forked bonds, the details of
+which are shown by Fig. 15, _A_, but, as it might have been impractical
+to use these if the wall had been built in sections, provision was made
+in the contract to place expanded metal, as shown by Fig. 15, _B_, if
+this was thought advisable. The method of construction necessary, if the
+wall had been built in sections, is shown graphically by the five
+sketches, Fig. 15, _B_, 1, 2, 3, 4, and 5.
+
+The form and details of the expanding mandrel which was finally designed
+to meet the conditions, and proved so satisfactory in every way, are
+shown by Fig. 15, _C_. The mandrel consisted of two triangular pieces of
+hard pine, separated by wedges attached to one piece which fitted into
+slots in the other; these, when expanded, practically filled the whole
+of the inside of the ducts. One of these mandrels was placed in each
+line of single ducts and two in each 4-way duct, placed diagonally, as
+shown in Fig. 1, Plate XXV. This required 60 mandrels at each working
+point, or 240 for the whole work. The mandrels were 35 ft. long, so that
+they easily covered the whole of a 25-ft. section, projected
+sufficiently far back into the previously finished work to assure the
+continuity of the alignment, and allowed the ends to be racked out at
+the forward end to secure proper breaks between the joints.
+
+In laying the single conduits, as a rule, the (collapsed) mandrels were
+pulled ahead from the previous section as each line was laid, and the
+conduits were strung on it until the whole length was completed; the
+conduits were then pushed up tight together, so as to close the joints
+as tightly as possible, and then the mandrel was expanded. The conduits
+were thus held firmly in position, and the forward end of the line was
+lifted slightly so that the wraps could be placed around the joints. The
+4-way conduits were generally laid in the ordinary way, except that no
+laying mandrel was necessary. One dowel was used between each of the
+pieces of conduit, at the center, and the joints were wrapped. When a
+line was finished, two mandrels were placed diagonally in each line and
+expanded simultaneously, so that any inequalities in the ducts
+themselves were divided as far as possible. In connection with the use
+of these mandrels, one of the points which was most carefully watched
+was that they projected back into the last completed section, thus
+insuring the continuity of the alignment.
+
+It was originally intended to wrap the joints of the 4-way ducts only,
+but it was found to be impractical to keep the grout from the wet
+concrete entirely out of the single ducts, and, after a short trial, it
+was decided to wrap these also. The expanding mandrel kept out a great
+deal of the cement, and, in the sections laid without wraps, the only
+difficulty from this cause seemed to be that a slight film of grout,
+from 1/16 to ⅛ in. thick, was deposited on the bottom of the inside of
+the ducts at some places, and although this was not considered a serious
+defect, it was thought that the slight extra cost of placing the wraps
+would undoubtedly be justified by the practically perfect results
+obtained by using them.
+
+Considerable attention was given to breaking the joints of the ducts
+properly, so as to maintain throughout the conduit lines the greatest
+break possible. The joints in each superimposed line were broken at half
+the length of the individual pieces of conduit, the joints in lines in
+the same horizontal plane being broken at one-quarter the length, thus
+preventing any joints from touching one another either at the sides or
+corners, which tended to prevent a burn-out on one line from being
+communicated to another. There was some little difficulty at first in
+maintaining the breaks, owing to slight variations in the lengths of the
+conduit, but after a very short time both the workmen and the inspectors
+became very expert at this and in the proper use of short lengths to
+maintain the spacing; after the first few weeks there was little if any
+difficulty in attaining at all times almost perfect results. The method
+of making the breaks is shown in the photographs and by the isometric
+sketch at _F_, Fig. 15.
+
+All the conduits used on this work were furnished by the Great Eastern
+Clay Company, and were made at its factory at South River, N.J., where
+they were inspected before shipment.
+
+The mandrel used in the final rodding was made as shown at _G_, Fig. 15,
+the larger size being used for all lines. The rods for pushing it
+through the conduit lines were made of 6½-ft. lengths of ordinary 1-in.
+wrought-iron pipe with extra long (3-in.) couplings. The lines were
+rodded in both directions from alternate manholes, thus avoiding
+uncoupling the rods and allowing every pull to be effective in pushing
+the mandrel through the ducts.
+
+ [Illustration: Fig. 15. [Full Page]
+ ELECTRICAL CONDUITS: METHODS OF LAYING, RODDING, ETC.
+ A. FORK ENDED STEEL BONDS FOR CONDUITS.
+ B. SEQUENCE OF METHODS OF BUILDING BENCH-WALL PROPOSED WHEN USING
+ EXPANDED METAL BONDS.
+ C. ISOMETRIC DRAWING OF EXPANDING MANDREL.
+ D. DETAILS OF “WEASEL” Used for gripping disconnected pipe rods in
+ conduit
+ E. CUTTER FOR REMOVING OBSTRUCTIONS IN CONDUITS.
+ F. ISOMETRIC SKETCH SHOWING METHOD OF BREAKING JOINTS AND POSITION
+ FORKED BONDS.
+ G. PLAN AND SECTIONS OF EXPANDING MANDREL.
+
+ INDEX
+ +-----+------------+-------------+
+ | | Multi-Duct | Single-Duct |
+ | | Mandrel | Mandrel |
+ +-----+------------+-------------+
+ | _A_ | 3¼” | 3⅜” |
+ | _B_ | ¾” | ⅞” |
+ | _C_ | 2½” | 2⅝” |
+ +-----+------------+-------------+
+
+ Note
+
+ End pipe connections may be changed to suit connections of rodding
+ outfit, care being taken to use a connection which will not split and
+ expand the mandrel if it should be driven back into it, in attempting
+ to ram the mandrel back when stuck in a duct.
+
+ Connection at Head End may be dispensed with, if the mandrel is
+ threaded through ducts by rods attached to the trailing end.]
+
+Wooden rods were used at first, but proved entirely too light, as the
+mandrels used were a close fit, and it required considerable effort to
+push them through 400 ft. of conduit. Iron pipe with ordinary couplings
+was next tried, but the couplings broke quite often, as the threads
+became worn in uncoupling the sections to move the rods from one line to
+another, and the break was generally inside a duct line. The long
+couplings were finally adopted, and a set of rods was put in each line,
+that is, six sets in all, so that when coupled up they remained in the
+line until it was finished. The expense of the extra quantity of pipe
+thus required was more than offset by the decreased labor cost.
+
+It was thought necessary at first to run a cutter, Fig. 15, _E_, through
+the conduits ahead of the final rodding mandrel, but this was soon found
+to be unnecessary except in a very few instances, and, after a short
+experience, the cutter was only used at places where an obstruction was
+encountered by the mandrel.
+
+At such times as the pipe became uncoupled inside the duct line, the
+part remaining inside was recovered by the use of the tool shown at _D_,
+Fig. 15, called a “weasel.” In two instances, the mandrel became stuck
+in such a manner that the duct line had to be cut into in order to take
+it out.
+
+The best day’s work of the rodding gang (1 foreman and 4 men) was 20,400
+duct ft. of the 4-way conduit in the telegraph and telephone line, and
+19,200 duct ft. of single conduit on the low-tension line, an average
+day’s work under ordinary conditions being about 10,000 duct ft. The
+cost, including labor, material, and all tools, for rodding for the
+whole work was slightly less than 0.2 cent per duct ft. The average cost
+of the single conduit was about 0.25 cents per ft., and of the 4-way,
+0.15 cents per ft. About 10% of the conduit lines were rodded twice,
+owing to partial sections having been rodded once before completion. The
+best continuous work on rodding was done between October 22d and 29th,
+1908, when in 7 working days, 105,600 duct ft. were rodded, an average
+of a little more than 15,000 ft. per day.
+
+
+_Bench-walls._--The original design for the tunnels provided for the
+construction of a brick arch above a point 22° above the springing line,
+that is, the part above the side-walls (Fig. 10). It was thought
+desirable, therefore, in designing the bench-wall forms, to provide for
+placing the concrete in the side-walls and bench-walls at one operation.
+These forms, as first designed, are shown by Fig. 2, Plate XXV, and the
+details in Fig. 16, _A_ and _A’_; they were built of steel, the facing
+plates being 5/16 in. thick, in pieces 4 ft. 6 in. wide, and in length
+about 6 in. more than the height of the bench-wall.
+
+ [Illustration: Fig. 16. [Full Page]
+ DETAILS OF TRAVELING FORMS USED IN THE CONSTRUCTION OF THE BENCH WALLS
+ A’. CROSS-SECTION OF STEEL FORM
+ A. LONGITUDINAL SECTION AND ELEVATION OF STEEL FORM USED AT
+ WEEHAWKEN END
+ B. DETAILS OF SCREW-JACKS FOR ADJUSTING FORM TO LINE
+ C. SECTION _C_-_D_ SHOWING CONNECTION OF FACE PLATES TO I-BEAM
+ UPRIGHTS
+ D. DETAILS OF WOODEN FORMS USED AT WESTERN END: CROSS-SECTION,
+ PART LONGITUDINAL SECTION
+ No chutes were used with these forms, the wheel-barrows being dumped
+ from the runways on the sides.]
+
+The design was controlled very largely by the necessity of providing the
+requisite clearance for the locomotives and muck cars, and the principal
+feature was the support of the forms on two trusses, one at either side,
+the front ends of which were supported from the foundation on a long
+leg, as shown in Fig. 3, Plate XXV, and the rear ends directly on the
+journal-boxes of wheels traveling on a rail on the top of the finished
+bench, as shown in Fig. 2, Plate XXV.
+
+Although it had been decided to substitute concrete for brick in the
+arch before any of the lining was actually placed, two sets of forms for
+the Weehawken end had already been ordered and delivered, so it was
+decided to use them as designed, and place the side-wall with the bench.
+
+The forms were designed so that 30-ft. lengths could be built, and this
+was done at the start, but owing to the occurrence of the refuge niches,
+ladders, etc., at 25-ft. intervals, it was soon seen that it would be
+advisable to build the bench-wall in sections of that length (25 ft.),
+or multiples of it, and as the clearance conditions seemed to preclude
+the possibility of making the forms 50 ft. long, 25 ft. was adopted.
+This permitted the removal of one of the panels, 4 ft. 6 in. wide, and
+at the same time it was decided to remove the side-wall forms. This
+decreased the load on the trusses considerably, but being still a trifle
+weak, they were strengthened by the substitution of 1¼-in. truss rods
+instead of the ¾-in. rods used originally. The top platform and the
+cross-bracing were also stiffened a little and tightened up to prevent
+racking.
+
+The construction of the side-walls in conjunction with the bench-wall
+was abandoned for three reasons: First, it was found that there would be
+a much more even distribution of the work by including the side-wall
+with the arch rather than with the bench; second, there was difficulty
+in getting a good finish for the top of the bench-wall, as of course a
+top form for the latter had to be placed to prevent the concrete from
+squeezing up when the side-wall was built above it, which prevented
+troweling; the third reason was the weakness of the whole form as
+designed, and the increasing difficulty of adjusting it to line as the
+work progressed, the principal difficulty being with the curved
+side-wall forms.
+
+The bench-wall forms were set in position, after they had been moved
+ahead, by first blocking the bottom against the face of the foundation,
+as shown by Fig. 13. As previously noted, this foundation face had been
+built very carefully to line. The back end of the form, of course, was
+blocked tightly against the end of the previously finished section, and
+the top was made plumb by the adjusting screwjacks shown in Fig. 16,
+_B_. At first these screws were ¾-in., but they were afterward changed
+to 1¼-in. The only points which it was necessary for the alignment corps
+to give in setting these forms was a grade at each of the front ends for
+the top of the finished bench.
+
+The steel face forms in both tunnels gave excellent results, as far as
+smoothness of finish was concerned, but, owing to the imperviousness of
+the steel, small air holes were formed in the surface, though not in
+sufficient numbers or size to cause trouble or disfigure the work in any
+way.
+
+The design of the bench-wall forms used at the western end, where this
+differs from the steel form, is shown by Fig. 16, _D_. The principal
+features in which they differed from those used at the Weehawken end was
+in the substitution of 2½-in. tongued and grooved hard pine for the
+face. This timber was of the very best quality obtainable, each piece
+being especially selected and as nearly clear and free from knots or
+other defects as it was possible to get it. The edges of each piece were
+planed at the back so as to insure a tight joint on the face, and all
+joints were shellacked. These forms were used, without renewal of the
+face timber and with only two planings, for a length of 2,500 ft., or
+100 separate sections, and gave good satisfaction.
+
+In order to obtain a surface to which the face lagging could be
+fastened, wooden uprights were used and were reinforced on either side
+by light channels bolted together through the timber, in place of the
+=I=-beams used on the steel forms. The lagging was nailed to these
+uprights by 6-in. wire nails driven through the top edges of each piece
+as it was placed in position, thus leaving the surface entirely clear
+and free from any marks or nail holes, and in condition for planing when
+this became necessary. Runways for wheeling the concrete were built one
+either side over the bench-walls instead of having a center platform
+with chutes, as was used at Weehawken.
+
+When the original lagging had become too much worn for further use, it
+was resurfaced with strips of ⅞ by 2½-in., clear, tongued and grooved,
+hard pine, placed vertically, which did fairly well and lasted to the
+end (about 1,000 ft.), although it was not altogether satisfactory, and
+the last eight or ten sections built had to be rubbed down with a wooden
+float in order to obtain a suitable finish.
+
+In designing the forms for all exposed surfaces in the tunnels, it was
+the desire of the contractors to obtain directly from them a surface
+which would be satisfactory to the engineers without further finishing
+than the patching of minor defects. In this they were generally quite
+successful, and excellent results were obtained, as shown in the view of
+the finished tunnel, Fig. 2, Plate XXVII. The surface of the bench-walls
+was obtained solely by spading the face with a flat spade as the work
+progressed. No after treatment was resorted to, except for the few
+sections where the forms became worn. The top of the bench-wall was
+finished with a float about 2 or 3 hours after the concrete was placed.
+
+When the work was well organized, a bench-wall was built at each end
+each day, one day in the North Tunnel, and the following day in the
+South. During the time sand-walls were being built, a sand-wall and
+bench-wall were built on alternate days in each tunnel, care being taken
+that when a bench-wall was being built in one tunnel, the sand-wall was
+being built in the other, this being necessary in order to equalize the
+work of the night gang and the conduit layers as well as the
+transportation.
+
+The conduit layers on the day shift, two or three men and a foreman,
+required about 2 hours in the forenoon and 1 hour in the afternoon to
+lay their portion of the conduits, and usually finished this work by 3
+P.M. At other times during the shift they were utilized at those points
+where rock packing was heaviest, and when the packing was brought in in
+the large cars, as shown in Fig. 1, Plate XXVI, these men helped unload
+it so that the track could be cleared as soon as possible. When
+water-proofing was to be done, the number of men in this gang was
+increased, so as to enable them to do that work also.
+
+ [Illustration: Plate XXVI.
+ Fig. 1: K 167. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) View of form for circuit breaker chamber at Sta. 286, and
+ travelling gantry for placing concrete in arches, looking Easterly
+ from near Sta. 280+85, South Tunnel. Oct. 3, 08.
+ Fig. 2: K 166. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) View of forms for storage chamber at Sta. 294+24, looking
+ Southward. Sept. 17, 08.
+ Fig. 3: K 163. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) Tunnel lining. Rock packing over arches, South tunnel Sta.
+ ???+?? end of completed section. May 19, 08.
+ Fig. 4: K 168. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) Showing method of waterproofing in timbered tunnel section
+ at Weehawken end. Oct. 21, 08.]
+
+A gang of four rough carpenters and a foreman was employed on the day
+shift; they moved and set the bench-wall forms or sand-wall forms, as
+the case might be, and moved the traveling gantry into position. This
+was done in the afternoon, and required about 3 hours. They also took
+out, cleaned, repaired, and set all ditch forms, all passenger forms,
+circuit-breaker forms, and did all other repair work. The ladder forms,
+the refuge-niche forms, and overhead conductor pocket forms were
+attended to by one man, who set, removed, cleaned, and repaired them.
+The carpenters on the night shift set the arch centers and gantries,
+also the manhole forms when needed. The conduit layers on the night
+shift laid up half the 4-way conduits (3-high) and one-third of the
+single ducts (4-high). This one gang laid the conduits in two sections
+of bench-wall each night, that is, one section at Weehawken and the
+other at the western end.
+
+In concreting the bench-walls, the concrete was first placed on the side
+containing the single conduit until it reached the top of the four tiers
+laid, then the concrete gang was turned over to the side with the 4-way
+conduits while four more tiers of single conduits were laid, the work
+thus progressing, the conduits being laid on one side while concrete was
+placed on the other. On the side of the 4-way conduits the concrete was
+built in two layers while that on the side of the single ducts was built
+in three; the interval between the different layers was not sufficiently
+long to prevent a complete bond being obtained, and there were only one
+or two instances where there was any mark on the face to indicate a
+break.
+
+After the work had been in progress some time, it was found to be quite
+feasible to build all the 4-way conduits at night and half the single
+conduits, that is, 6 ducts high, as the mandrels proved amply sufficient
+to hold them in place; in fact, had it been necessary, the writer has no
+doubt that all the ducts might have been laid and held in place with
+very little extra precaution, by the use of the expanding mandrels,
+as described under the head of conduit laying. A =V=-shaped joint about
+½ in. deep was made between each section of bench-wall so that the
+expansion cracks would follow this joint rather than show irregularly on
+the face. These joints divided the face into the even 25-ft. panels, and
+were very effectual in concealing what few cracks there were.
+
+After the construction of the sand-walls was discontinued, the space
+behind the bench-walls, between the neat line and the rock, was filled
+with rock packing, which was generally built, part way up at least, as a
+dry wall ahead of the construction of the bench-wall, or it was put in
+place simultaneously with the concrete, care being taken to keep it as
+free as possible for the drainage of any water there might be. Toward
+the latter part of the work, owing to the difficulty of getting
+sufficient rock packing during the day, a rough back form for the
+bench-wall was built at the neat line, in places where the section was
+at all large, and the space was filled with rock afterward, generally at
+night or on Sundays.
+
+In the sections where water-proofing was required, where no sand-wall
+was built, the rock was taken out for 2 ft. outside the neat line,
+if the excavation was not already that far out (at the expense of the
+contractors, who preferred to do this rather than build the sand-walls
+for the short sections required), so that there would be sufficient room
+for placing the water-proofing on the back of the bench-walls, as shown
+by Fig. 18, _E_. The water-proofing of these sections was left until
+just before the arch was to be built, and after being placed it was
+protected by a single row of brick laid on edge before the rock packing
+was filled in.
+
+
+_Arches._--The centering used for the arches is shown very clearly in
+Fig. 4, Plate XXV, which is a view of the back end of the first section
+built at Weehawken. In this part of the tunnel, the lower part of the
+arch, about 5 ft. above the bench-wall, was built first, as previously
+referred to, but the centers, as will be seen, were built so that they
+could be used for the whole of the arch. The forward bulkhead, and the
+shoveling platform on a section being built, are shown in Fig. 3, Plate
+XXVI.
+
+The front bulkheads used were made in nine sections, bolted to a 2½ by
+2½-in. angle bent to the radius of the arch, as shown in Fig. 3, Plate
+XXVI, and fitting on the end of the lagging; when set they were braced
+partly against the rock of the roof and partly against the gantry. After
+the ribs and part of the lagging had been set by the night gang for a
+fresh section of arch, the braces holding the bulkheads were knocked
+out, the concrete placed during the day having set sufficiently by this
+time; the whole of the bulkhead was then easily moved ahead, sliding
+along the lagging to the forward end, and made ready for the next day’s
+work. The middle section at the top was taken out temporarily, to
+facilitate working at the sides, until it was needed.
+
+The traveling gantry used in handling the concrete for the arch is shown
+in Fig. 1, Plate XXVI, which also shows the form for the circuit-breaker
+chamber, and a car of rock packing on the track beneath.
+
+The arches were built in 10-ft. sections, the ribs being spaced 5 ft.
+apart, the end ribs of each section supporting the end of the lagging on
+two adjoining sections. Five sets of lagging and ten ribs were used at
+each place where the arch was being built, thus giving each section
+practically 4 days’ set before removing the centers. Probably in the
+greater part of the work the centers could have been removed in from 40
+to 48 hours after the concrete had been placed, but 3 days was
+considered the least time which would certainly be safe at all times,
+and the contractors thought that the very slight additional expense
+involved in leaving the centers up 4 days was more than warranted by the
+additional feeling of security.
+
+The lagging was made from 3 by 6-in. clear, hard pine, 10 ft. long,
+dressed to about 2½ in. in thickness, about 5½ in. in width, and the
+sides to radial lines. As it was placed, every third or fourth piece was
+lightly nailed to the ribs; when the latter were released and taken
+down, the nails pulled out, and the lagging was left in place until one
+piece was pried out, allowing the others to fall. A light =A=-frame,
+about 8 ft. long, spanning the bench-walls, was placed below, in order
+to break the fall and allow the lagging to slide to the top of the
+bench-walls rather than fall to the track beneath.
+
+Cross-passages between the two tunnels were built every 300 ft., their
+form being shown on Plate VIII of the paper by Mr. Jacobs. There were
+two circuit-breaker chambers, one at Station 286 and the other at
+Station 310. Steel doors are provided so that all the openings between
+the two tunnels can be closed. At Station 294+24, the core-wall broke
+through for a length of about 40 ft., and instead of filling this in,
+a storage chamber 34 ft. long and 11 ft. wide, inside, was built there,
+the form for which is shown in Fig. 2, Plate XXVI. This photograph, as
+well as Fig. 1, Plate XXVI, a form for a circuit-breaker chamber, shows
+the method of setting the steel doors in the forms, so that they were
+built into the concrete instead of being fastened in with expansion
+bolts afterward, thus showing a perfect fit and a much neater job.
+
+During construction the arches in each tunnel were kept even with each
+other, so that when the cross-passages were reached, they, and the
+sections of arch which they joined, could be completed at one operation.
+
+By the methods used on this work, one section of arch was easily built
+in a shift, so that the monolithic construction of each section was
+easily secured, and concrete, as wet as it was possible to handle with
+shovels, could be used for all except the last 5 ft. or so at the top,
+thus getting a structure which was as nearly impervious as possible
+under the circumstances.
+
+The gangs placing the arches were paid over-time when they were required
+to work after 6 o’clock to finish their section, which was generally
+only necessary when the quantity of rock packing to be placed was very
+large. If they finished their section before 6 o’clock, however, they
+were allowed to quit when this was done, and were given a full day’s
+pay. The difference in time, when there was any, was usually due to the
+greater or less quantity of rock packing, as the excavation varied from
+the standard section line.
+
+In building the arches, the night gang set the two ribs (one at the
+center and one at the forward end of the section to be built), placed
+the lagging on the sides, 4 or 5 ft. high, built the shoveling platform
+on the horizontal cross-braces of the ribs, and placed the traveling
+gantry in position for use. The forward end of the gantry (that is, the
+end farthest from the arch being built), as shown in Fig. 1, Plate XXVI,
+was loaded with rock packing to be used as required. As the concrete was
+brought into the tunnel it was hoisted and dumped on the end of the
+gantry next the arch, and shoveled from there to the platform on the
+ribs and from there into place. The rock packing brought in during the
+day was dumped on the front or back end of the gantry, as was most
+convenient, and handled into the work in the intervals between batches
+of concrete. The concrete and rock packing, with the back-lagging and
+water-proofing, where these were used, were placed simultaneously, or
+nearly so, and brought up the sides together until the key was reached;
+the latter was then worked from the back toward the front. The key was
+usually made about 5 ft. wide, the lagging for this width was made 5 ft.
+long and put up in two sections. It was found to be more convenient to
+have the key of this width than narrower.
+
+The method used in making the closures where two sections of the arch
+came together is shown by Fig. 17.
+
+ [Illustration: Fig. 17. [Full Page]
+ SKETCH SHOWING METHOD OF MAKING ARCH CLOSURE
+ CROSS-SECTION OF TUNNEL SHOWING JACK PARTLY EXTENDED
+ LONGITUDINAL SECTION OF TUNNEL SHOWING JACK PARTLY EXTENDED
+ PLAN OF BOX; END VIEW
+ PLAN OF PLUNGER, BOTTOM OF BOX; END VIEW OF PLUNGER,
+ JACK FULLY EXTENDED]
+
+
+_Water-proofing._--As already pointed out, the original design for the
+lining of these tunnels provided for a brick arch. It was intended to
+cover this arch with water-proofing, this latter extending over the
+whole of the roof and down the sides as far as the bottom of the conduit
+lines. The water-proofing was to be placed against the sand-walls on the
+sides, up to the top of the side walls, Figs. 10 and 14. Over the arch,
+after being placed, it was to be protected by an armor course of brick,
+laid flat, the space between the brick and the excavation, which was
+required to be not less than 4 in. (and, as a matter of fact, was
+actually a great deal more), being filled with rock packing. Besides
+filling the space, this latter was designed to allow any water from the
+roof of the tunnel to find its way easily to the top of the sand-wall,
+from there being carried through the 4-in. cast-iron pipes, shown on
+Plate VIII[4] to the side ditches in the floor of the tunnel.
+
+ [Footnote 4: Of the paper by Mr. Jacobs.]
+
+All the water-proofing placed in these tunnels was of felt and pitch,
+six-ply felt and seven layers of pitch. The felt was required to be
+Hydrex, or of equal quality, and the pitch, “Straight run coal-tar pitch
+which will soften at 60° Fahr., of a grade in which the distillate oils
+will have a specific gravity of 1.05.”
+
+In addition to tests as to the above qualities, the pitch was analyzed
+to determine the amount of free carbon it contained, and was not
+accepted if this fell below 20 per cent.
+
+It was considered quite important that there should be absolutely free
+drainage on the outer side of the lining, so that there would be no
+chance for any water to acquire a head. More than three-quarters of the
+length of these tunnels is below the level of mean high water, and while
+it was hardly expected that there would be any direct connection between
+the water in the Hudson River and the groundwater of the section
+penetrated, it was thought wise to provide ample drainage.
+
+Before the lining was started, however, the excavation had progressed
+sufficiently to show that the tunnels, while very wet in places, and
+varying from that to quite damp, would be, on the whole, much dryer than
+had been anticipated. It was then decided to substitute concrete for the
+brick in the arch and omit the water-proofing over the top, except at
+places where water came into the tunnels in sufficiently large
+quantities to form practically a continuous stream. Three general types
+of construction for the arch were decided on, as shown in Fig. 18. The
+first, as shown at _A_, was to be used where the tunnel was quite dry.
+In this type, the sand-wall was omitted entirely, and the concrete and
+rock packing were built up together, the rock packing impinging to a
+certain extent on the concrete, and the concrete squeezing somewhat into
+the rock packing, as shown by Fig. 4, Plate XXV. The section shown at
+_B_ was used where the tunnels were damp, or where there were slight
+droppers not forming a continuous stream. The back lagging, of 1-in.
+boards, which was left in place, provided a practically smooth outer
+surface on the concrete arch, and allowing the concrete and rock packing
+to be built almost simultaneously. It was considered that the free
+drainage through the rock packing, the surface of the boards, and the
+smooth outer surface of the concrete in the arch would allow the
+comparatively small quantity of water in these parts of the tunnel to
+find its way to the sides, and thence to the ditches at the bottom,
+rather than to percolate through the concrete, and this proved to be
+very generally the case, as is shown by the dry condition of the tunnel
+as built. The back lagging was used over the arch, both where the
+sand-wall was built and where it was omitted, as well as being placed
+over the water-proofing of the arch as an armor course where
+water-proofing was required. Where the sand-walls were built and
+water-proofed, and where the water-proofing was not carried over the
+arch, the water-proofing was turned in at the top, as shown at _C_, Fig.
+18.
+
+ [Illustration: Fig. 18. [Full Page]
+ VARIOUS TYPES OF ARCHES, AND WATER-PROOFING USED
+ Method of Lapping Mats over Arch
+ Method of making joint when work on section was not continuous. Part
+ of joint on radial line, part sloping slightly toward outside of
+ arch.
+ DETAILS OF WATER-PROOFING
+ One layer of felt with 4" overlap to be nailed to lagging of inch
+ boards, using tin washers on nails over the whole of the intrados
+ of the arch before starting any concrete or placing any of the
+ permanent felt and pitch water-proofing. The water-proofing over
+ the arch can be laid in mats of three thicknesses of felt properly
+ joined together with pitch made as shown diagrammatically at “_x_”
+ Each of these mats of three-ply felt will be overlapped half the
+ width of the mat, as shown diagrammatically at “_y_”]
+
+The third method provided for water-proofing the whole of the arch, and
+was the same as _B_ except for the addition of the water-proofing inside
+the back lagging. In placing this water-proofing, the felt was cut in
+strips about 11 ft. long (about 1 ft. longer than the length of a
+section of arch), and six thicknesses were cemented together with hot
+pitch. These mats were then laid shingle-fashion, as shown at _D_, Fig.
+18, up the sides of the arch until a space about 5 ft. wide remained at
+the crown; shorter mats were then brought out over this, laying them
+perpendicular to the axis of the tunnel. Care was taken in making all
+laps, irrespective of the direction in which the arch was built, so that
+they would lay with the grade, that is, so that the water would tend to
+flow over the edges of the laps rather than against them.
+
+Most of the wet sections of the tunnel were at the ends, where
+sand-walls had been built for the purpose of providing a smooth surface
+against which the water-proofing was to be placed; there were several
+wet places at isolated points in the tunnels, however, and, in order to
+avoid building sand-walls at these points, the method shown at _E_, Fig.
+18, was adopted. This involved a slightly larger excavation, 2 ft.
+outside of the neat line, up to the height of the top of the bench,
+where there was not already that much room. The bench-wall was built
+with a back form on the neat line, the water-proofing was placed as
+shown, protected by an armor course of brick, and then continued over
+the arch when this latter was built. The excavation and refilling with
+rock packing were done at the contractor’s expense, which he was willing
+to assume rather than build these short sections of sand-wall.
+
+ [Illustration: Plate XXVII.
+ Fig. 1: K 181. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) Timbered section near Weehawken Shaft, showing method of
+ placing waterproofing and keying arch. Dec. 8, 08.
+ Fig. 2: K 184. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels). View of completed tunnel looking Eastward from Sta.
+ 323+60. South Tunnel. Feb. 8, 09.
+ Fig. 3: K 149. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels) Hackensack Portal, general view of completed Portal, and
+ arches through cut and cover section looking East. Oct. 15, 07.
+ Fig. 4: K 190. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill
+ Tunnels.) Hackensack Approach. General view, looking East. March 16,
+ 09.]
+
+The method of water-proofing that part of the timbered section which was
+very wet, is shown at _F_, Fig. 18, and in Fig. 4, Plate XXVI, and
+Fig. 1, Plate XXVII. A lagging of 1-in. boards was nailed up the sides
+and to the soffit of the segmental timbering, all the spaces outside of
+this lagging being carefully filled with rock packing. Before starting
+any concrete work, a single thickness of water-proofing felt was nailed
+to the inner side of the lagging, which not only served to protect the
+finished surfaces of the concrete from the water which fell copiously
+from the roof, but also provided a comparatively dry surface to which
+the regular six-ply water-proofing could be cemented with pitch and held
+in position, while the concrete was placed against it.
+
+In placing the water-proofing in this section on the sides, the strips
+of felt were placed vertically, nailed at the top to the wall-plate, to
+support their weight, and lapped and cemented with pitch to the sides as
+on the sand-walls, except that there was no trouble from the overhang.
+After the bench-wall had been built, the felt was cut just below the
+nails and about 2 ft. above the top of the bench, so that the mats which
+were placed over the arch could be inserted behind it. The roof was
+covered with three-ply mats and lapped over a little more than half, as
+shown diagrammatically on the drawing.
+
+When the upper part of the arch was reached, where the cementing
+strength of the pitch was not sufficient to hold the felt in place, the
+mats were braced temporarily from the centering, as shown by Fig. 1,
+Plate XXVII, until the concrete could be packed against it.
+
+Where the water-proofing was placed against the sand-wall, the method of
+securing the sheets at the top is shown in the small sketch on Fig. 14
+and by Figs. 3 and 4, Plate XXIV. Fig. 3, Plate XXV, shows the laps of
+the sheets and the method of hanging. At the start an attempt was made
+to stick the water-proofing to the sand-wall, but this could not be done
+on account of its dampness and the overhang at the top.
+
+The sand-wall water-proofing was kept about 35 ft. ahead of the finished
+bench-wall, as shown by Fig. 3, Plate XXV. As the bench-wall form was
+moved ahead and set, the mat was braced back against the sand-wall from
+the forms at a point just above the top of the finished bench, care
+being taken to avoid wrinkles, as, if these were once formed, it was
+practically impossible to straighten them out.
+
+The completion of the bench-wall left the upper part of this
+water-proofing stretched taut across the curved top of the sand-wall,
+forming a chord of the arc. As the arch was built up, the top was
+gradually slackened so as to allow the concrete to press the mat back
+into place until the top of the sand-wall was reached, when the end was
+turned in, as shown at _C_, Fig. 18, or the water-proofing was continued
+over the arch, if that was necessary.
+
+The desire to obtain a dry tunnel, and the methods adopted to secure it,
+were responsible in a great measure for the decision to build the arch
+in short lengths, as well as the reasons given under the head of arches.
+Had the tunnels been dry throughout, the method shown at _A_, Fig. 18,
+could have been used exclusively, and, except for the fact that
+monolithic concrete might not have been obtained, there would have been
+no objection to building longer lengths.
+
+The quantity of water reaching the tunnel drains and flowing out of
+their lower ends after the completion of the lining was about 100,000
+gal. per day, or 75 gal. per min.; of this it is estimated that
+considerably less than 1% comes through the lining in the form of leaks.
+The very general distribution of this water over the roof is indicated
+by the fact that, during the excavation of the first 1,000 ft. of both
+tunnels from the Weehawken end, oilskins had to be provided for the
+laborers to induce them to work at all. The success, therefore, of the
+rock packing as a means of diverting this water to the side drains, is
+shown, especially in view of the fact that, excluding the cut-and-cover
+section, only 10% of the length of the arch, 1,189 ft., was
+water-proofed.
+
+Considerable care was taken to make all joints in the concrete which
+were in such a position that water might follow through them to the
+inside of the tunnel lining, in such a manner that they would slope
+outward toward the rock. The top of the sand-wall is shown by Figs. 14
+and 18. The slope of the back of the foundation may be noted in Fig. 18,
+and the method of making the joint in the arch, in the few instances
+where a section was not completed at one operation, is shown at _A_,
+Fig. 18. These joints in the arch were not allowed to be made above a
+point 60° above the springing line.
+
+
+HACKENSACK PORTAL AND APPROACH.
+
+The approach cut at the western end is 300 ft. long, the alignment being
+a 2° curve, as shown in Fig. 19. The bench-walls and conduit lines built
+throughout the length of the tunnels are extended through the approach
+cut, the top of the former gradually sloping from the portal to the
+mouth of the cut, where they are just level with the top of the rail,
+the conduits also being depressed to the same relative position with the
+tops of the benches.
+
+ [Illustration: Fig. 19. [Full Page]
+ BERGEN HILLS TUNNELS.
+ Hackensack Portal and Approach.
+ SECTIONS AND ELEVATIONS.
+ PLAN OF APPROACH.
+ PROFILE THROUGH APPROACH.
+ SECTION SHOWING METHOD OF MAKING JOINT BETWEEN COPING AND WALL.
+ PLAN SHOWING METHOD OF MAKING JOINT BETWEEN ADJOINING SECTIONS.
+ SECTION OF BENCH AND RETAINING WALLS AND HALF ELEVATION OF PORTAL.]
+
+The top of the rock at the mouth of the cut, Station 327, was from 4 to
+6 ft. below the top of the rail, and gradually rose through the approach
+until at the portal it was about 6 or 8 ft. above the roof of the
+tunnel. The rock was covered with hardpan. A profile of this part of the
+work is shown on Fig. 19. The rock throughout the approach was
+water-bearing to a considerable extent, and a face-wall was built at the
+sides with free drainage, through rock packing and vitrified and
+cast-iron drains behind it, to keep this water from flowing over the
+tops of the bench-walls, and also to keep the lines of conduits dry.
+
+The retaining walls were built in 25-ft. sections, the joints
+corresponding to those in the benches, being at the even stations, +08,
++33, +58, and +83. =V=-shaped joints were made down the face, and the
+ends of the sections were made as shown by Fig. 19. The back part of the
+joint was mopped with hot pitch before the next section was built, so
+that there was practically no bond between any two adjoining sections.
+
+The concrete in these walls was placed late in the season, and the
+expansion cracks, which were entirely confined to the =V=-shaped joints,
+were quite small even in the coldest weather of the following winter,
+nor were there any indications during the past summer of any stresses
+due to expansion. The coping and drain at the top of the wall were built
+together, but separate from the rest of the wall, the joint being made
+as shown in the sketch on Fig. 19. Thus far, there has seemed to be no
+seepage through either the vertical or horizontal joints.
+
+The portal is built of granite, a half elevation being shown on Fig. 19,
+the stone being supplied by the Millstone Granite Company, Millstone
+Point, Conn. Fig. 3, Plate XXVII, shows the portal and the cut-and-cover
+section after the arches were completed but not covered.
+
+The forms for the concrete in the approach were made of ordinary dressed
+lumber, and the surface was rubbed twice after the forms were removed,
+which was as soon as possible after the concrete had set. The surface
+was first very lightly rubbed with a piece of soft, light-colored,
+sandstone to remove any irregularities, being wetted slightly if
+necessary while being rubbed. After the concrete had become fairly hard
+and dry, it was rubbed a second time and a uniform texture and color
+obtained. The completion of this work was delayed until the second week
+in January, and considerable difficulty was encountered in obtaining a
+good finish of that part which was built after cold weather set in, when
+it was necessary to protect it from frost. Unless extreme care was taken
+to prevent freezing after the rubbing, the entire surface was likely to
+scale off, although no cement or other material was added to it after
+the removal of the forms. A general view of the completed approach is
+shown by Fig. 4, Plate XXVII.
+
+ TABLE 6.
+
+ ---------------------+----------------------+-----------------------+
+ | DAY. | NIGHT. |
+ Title. +-----+-------+--------+-----+-------+---------+
+ | No. | Rate. | Amount.| No. | Rate. | Amount. |
+ ---------------------+-----+-------+--------+-----+-------+---------+
+ Walking bosses | 2 | $5.00 | $10.00 | | | |
+ Timekeeper | 2 | 3.00 | 6.00 | | | |
+ Watchmen | | | | 5 | $2.00 | $10.00 |
+ Waterboys | 1 | 1.50 | 1.50 | | | |
+ Carpenter foremen | 2 | 3.50 | 7.00 | 1 | 4.00 | 4.00 |
+ Carpenters | 14 | 2.50 | 35.00 | 8 | 2.50 | 20.00 |
+ Pipe-fitters | 1 | 3.00 | 3.00 | | | |
+ Pipe-fitter’s helper | 1 | 1.75 | 1.75 | | | |
+ Wheelwright | 1 | 2.75 | 2.75 | | | |
+ Wheelwright’s helper | 1 | 1.75 | 1.75 | | | |
+ Blacksmith | 1 | 3.00 | 3.00 | | | |
+ Blacksmith’s helper | 1 | 1.75 | 1.75 | | | |
+ Foremen riggers | 1 | 3.00 | 3.00 | | | |
+ Riggers | 6 | 1.75 | 10.50 | | | |
+ Foremen trackmen | 1 | 3.00 | 3.00 | | | |
+ Trackmen | 6 | 1.50 | 9.00 | | | |
+ Machinist | 2 | 3.00 | 6.00 | | | |
+ Machinist’s helper | 1 | 1.75 | 1.75 | | | |
+ Electrician | 2 | 3.00 | 6.00 | 1 | 2.50 | 2.50 |
+ Electrician’s helper | 1 | 1.75 | 1.75 | | | |
+ Lampman | 1 | 1.50 | 1.50 | | | |
+ Pumpman | 1 | 1.50 | 1.50 | | | |
+ Finishers | 3 | 2.50 | 7.50 | | | |
+ Hoist engineers | 12 | 3.00 | 36.00 | | | |
+ Dinky engineers | 5 | 2.75 | 13.75 | 1 | 2.75 | 2.75 |
+ Brakemen | 5 | 1.75 | 8.75 | 1 | 1.75 | 1.75 |
+ Switchmen | 1 | 1.50 | 1.50 | | | |
+ Barnmen | 1 | 2.00 | 2.00 | 1 | 2.50 | 2.50 |
+ Drivers | 9 | 1.50 | 13.50 | | | |
+ Foremen ductmen | | | | 2 | 2.50 | 2.50 |
+ Ductmen | | | | 5 | 2.00 | 10.00 |
+ Foremen laborers | 13 | 3.50 | 45.50 | 2 | 3.50 | 7.00 |
+ Laborers | 120 | 1.75 | 210.00 | 20 | 1.75 | 35.00 |
+ Compressor engineer | 1 | 3.50 | 3.50 | 1 | 3.50 | 3.50 |
+ Firemen | 2 | 2.50 | 5.00 | 1 | 2.50 | 2.50 |
+ Oiler | 1 | 1.75 | 1.75 | | | |
+ Coal passers | 2 | 1.75 | 3.50 | 1 | 1.75 | 1.75 |
+ ---------------------+-----+-------+--------+-----+-------+---------+
+ Totals | 334 | |$469.75 | 50 | | $108.25 |
+
+ Total daily labor expense $578.00
+ ---------------------------------------------------------------------
+
+The water finding its way into the side ditches in the approach, which
+of course included all rain falling in this area, was intercepted just
+inside the portal and carried back to the mouth of the cut through
+24-in. cast-iron pipes laid beneath the conduits in the central
+bench-wall, thus disposing by natural drainage of a not inconsiderable
+quantity of water which would otherwise have flowed through the tunnels
+to the sump at the Weehawken Shaft, from which it would have had to be
+pumped to the surface.
+
+About 100 ft. of the tunnel immediately east of the Hackensack Portal
+was built by the cut-and-cover method, and the arch section used in the
+tunnel was modified by widening the haunches, the thickness of the arch
+at the crown being gradually increased from 22 in. at the portal,
+Station 324, to 34 in. at Station 323, where the regular segmental
+timbering at the tunnel commenced. A general view of the approach during
+construction is shown by Fig. 1, Plate XXV.
+
+
+CONTRACTOR’S ORGANIZATION.
+
+Table 6 shows approximately the number of men employed daily on the
+tunnel lining, by both the contractor and the sub-contractors, their
+occupation, the average rate of wages and the total daily expense for
+labor when the work was in full swing.
+
+
+ENGINEERING ORGANIZATION.
+
+The whole of the work of the North River Division was designed and
+executed under the direction of Charles M. Jacobs, M. Am. Soc. C. E.,
+Chief Engineer, and James Forgie, M. Am. Soc. C. E., Chief Assistant
+Engineer, the construction of Section “K,” Bergen Hill Tunnels, being
+directly in charge of the writer as Resident Engineer.
+
+ [Transcriber’s Note:
+ The two organizational charts, Figs. 20 and 21, have been reformatted
+ for space.]
+
+ [Chart: Fig. 20.
+
+ PENNSYLVANIA TUNNEL AND TERMINAL RAILROAD COMPANY,
+ SECTION “K”--BERGEN HILL TUNNELS.
+
+ Organization of Staff of Resident Engineer.
+
+ Organization Previous to the Holing Through of the Tunnels.
+
+ Resident Engineer.
+ _______________|________
+ | | |
+ Assistant | Assistant
+ Engineer. | Engineer.
+ _________|________ | |
+ | | | |
+ Cost and Office Field Inspection. Alignment.
+ Records.
+
+ Cost and Office Records.
+ Inspector.
+ Two Clerks.
+ Stenographer.
+ Telephone Operator.
+ Messenger.
+ Janitors.
+
+ Field Inspection.
+ Weehawken.
+ Chief Inspector.
+ Inspector, N. Tunnel
+ ” S. Tunnel.
+ ” Mixer.
+ ” Excavation and Force Account.
+ Inspector, Night.
+ Cement Warehouseman.
+ Conduit Inspector. (_one position_)
+ Hackensack.
+ Chief Inspector.
+ Chief Inspector.
+ Inspector, N. Tunnel
+ ” S. Tunnel.
+ ” Mixer.
+ ” Excavation and Force Account.
+ Inspector, Night.
+ Cement Warehouseman.
+ Conduit Inspector. (_one position_)
+
+ Alignment.
+ Weehawken.
+ Chief of Party.
+ Instrumentman.
+ Rodman.
+ Chainman.
+ Hackensack.
+ Chief of Party.
+ Instrumentman.
+ Rodman.
+ Chainman.]
+
+
+ [Chart: Fig. 21.
+
+ Organization After the Tunnels Had Been Holed Through.
+
+ Resident Engineer.
+ ________________|_______________
+ | | | |
+ Assistant | | Assistant
+ Engineer. | | Engineer.
+ _______|______ | | |
+ | | | | |
+ Cost and Office Field Inspection. | Alignment.
+ Records. _____|_____________|
+ | |
+ Tunnels. Conduit Inspector.
+
+ Cost and Office Records.
+ Two Inspectors.
+ Two Clerks.
+ Stenographer.
+ Telephone Operator.
+ Messenger.
+ Janitor.
+
+ Tunnels.
+ Chief Inspector.
+ 8 Tunnel Inspectors.
+ 2 Mixer Inspectors.
+ 1 Night Inspector.
+ Conduit Inspector.
+ Inspector, Hackensack Approach.
+
+ Alignment.
+ 1 Instrumentman.
+ 1 Draftsman.
+ 2 Rodmen.
+ 3 Chainmen.]
+
+The general organization of the staff is shown by the two diagrams,
+Figs. 20 and 21. Fig. 20 shows the organization previous to the holing
+through of the tunnels, during which time a separate office was
+maintained at the western end for the use of the men stationed there;
+Fig. 21 shows the organization during the latter part of the time, after
+the tunnels were holed through. The Assistant Engineer in charge of the
+construction was J. R. Taft, Assoc. M. Am. Soc. C. E.; the Chief
+Inspector, J. S. Frazer, Jun. Am. Soc. C. E., had charge of about 75% of
+the work of the lining of the tunnels. The alignment has been from the
+beginning under the charge of R. L. Reynolds, Assistant Engineer.
+
+ * * * * *
+ * * * *
+ * * * * *
+
+ Errors and Notes:
+
+ Each Plate was printed with the same header:
+ PLATE __.
+ TRANS. AM. SOC. CIV. ENGRS.
+ VOL. LXVIII, No. 1154.
+ LAVIS ON
+ PENNSYLVANIA R.R. TUNNELS: BERGEN HILL TUNNELS.
+ These headers were omitted for the e-text. Captions beginning in
+ “K” with a number were printed directly on the photograph; some
+ readings are uncertain and are indicated by question marks (?).
+
+ In the tables of Figures 1-4, variation between “to” and “-”, and
+ formatting of table entries, is as in the original.
+
+ [Fig. 1, table]
+ Per cubic yard, whole tunnel section: 3-33
+ _may be error for “3-3.3”_
+ [Fig. 1, last line of table]
+ Total Pounds
+ _text reads “Pound”_
+ Figs. 3 and 4, and Plate XXIV
+ _apparent error for “Figs. 3 and 4, Plate XXIV” (usual form)_
+ [Figure 15 A, B, C...]
+ _letters other than “B” do not appear in the printed Figure_
+ [Figure 15, caption]
+ DETAILS OF “WEASEL”
+ _quotation marks look hand-written, but printed text has spaces_
+ [Figure 15, “Index” (small table)]
+ Multi-Duct Mandrel
+ _text reads “Mult-Duct”_
+ which would be satisfactory to the engineers
+ _text reads “satifactory”_
+
+ Missing or superfluous punctuation was silently corrected.
+
+
+
+
+
+End of the Project Gutenberg EBook of Transactions of the American Society
+of Civil Engineers, vol. LXVIII, Sep, by F. Lavis
+
+*** END OF THIS PROJECT GUTENBERG EBOOK SOCIETY OF CIVIL ENGINEERS ***
+
+***** This file should be named 21083-0.txt or 21083-0.zip *****
+This and all associated files of various formats will be found in:
+ http://www.gutenberg.org/2/1/0/8/21083/
+
+Produced by Louise Hope, Juliet Sutherland and the Online
+Distributed Proofreading Team at http://www.pgdp.net
+
+
+Updated editions will replace the previous one--the old editions
+will be renamed.
+
+Creating the works from public domain print editions means that no
+one owns a United States copyright in these works, so the Foundation
+(and you!) can copy and distribute it in the United States without
+permission and without paying copyright royalties. Special rules,
+set forth in the General Terms of Use part of this license, apply to
+copying and distributing Project Gutenberg-tm electronic works to
+protect the PROJECT GUTENBERG-tm concept and trademark. Project
+Gutenberg is a registered trademark, and may not be used if you
+charge for the eBooks, unless you receive specific permission. If you
+do not charge anything for copies of this eBook, complying with the
+rules is very easy. You may use this eBook for nearly any purpose
+such as creation of derivative works, reports, performances and
+research. They may be modified and printed and given away--you may do
+practically ANYTHING with public domain eBooks. Redistribution is
+subject to the trademark license, especially commercial
+redistribution.
+
+
+
+*** START: FULL LICENSE ***
+
+THE FULL PROJECT GUTENBERG LICENSE
+PLEASE READ THIS BEFORE YOU DISTRIBUTE OR USE THIS WORK
+
+To protect the Project Gutenberg-tm mission of promoting the free
+distribution of electronic works, by using or distributing this work
+(or any other work associated in any way with the phrase "Project
+Gutenberg"), you agree to comply with all the terms of the Full Project
+Gutenberg-tm License (available with this file or online at
+http://gutenberg.org/license).
+
+
+Section 1. General Terms of Use and Redistributing Project Gutenberg-tm
+electronic works
+
+1.A. By reading or using any part of this Project Gutenberg-tm
+electronic work, you indicate that you have read, understand, agree to
+and accept all the terms of this license and intellectual property
+(trademark/copyright) agreement. If you do not agree to abide by all
+the terms of this agreement, you must cease using and return or destroy
+all copies of Project Gutenberg-tm electronic works in your possession.
+If you paid a fee for obtaining a copy of or access to a Project
+Gutenberg-tm electronic work and you do not agree to be bound by the
+terms of this agreement, you may obtain a refund from the person or
+entity to whom you paid the fee as set forth in paragraph 1.E.8.
+
+1.B. "Project Gutenberg" is a registered trademark. It may only be
+used on or associated in any way with an electronic work by people who
+agree to be bound by the terms of this agreement. There are a few
+things that you can do with most Project Gutenberg-tm electronic works
+even without complying with the full terms of this agreement. See
+paragraph 1.C below. There are a lot of things you can do with Project
+Gutenberg-tm electronic works if you follow the terms of this agreement
+and help preserve free future access to Project Gutenberg-tm electronic
+works. See paragraph 1.E below.
+
+1.C. The Project Gutenberg Literary Archive Foundation ("the Foundation"
+or PGLAF), owns a compilation copyright in the collection of Project
+Gutenberg-tm electronic works. Nearly all the individual works in the
+collection are in the public domain in the United States. If an
+individual work is in the public domain in the United States and you are
+located in the United States, we do not claim a right to prevent you from
+copying, distributing, performing, displaying or creating derivative
+works based on the work as long as all references to Project Gutenberg
+are removed. Of course, we hope that you will support the Project
+Gutenberg-tm mission of promoting free access to electronic works by
+freely sharing Project Gutenberg-tm works in compliance with the terms of
+this agreement for keeping the Project Gutenberg-tm name associated with
+the work. You can easily comply with the terms of this agreement by
+keeping this work in the same format with its attached full Project
+Gutenberg-tm License when you share it without charge with others.
+
+1.D. The copyright laws of the place where you are located also govern
+what you can do with this work. Copyright laws in most countries are in
+a constant state of change. If you are outside the United States, check
+the laws of your country in addition to the terms of this agreement
+before downloading, copying, displaying, performing, distributing or
+creating derivative works based on this work or any other Project
+Gutenberg-tm work. The Foundation makes no representations concerning
+the copyright status of any work in any country outside the United
+States.
+
+1.E. Unless you have removed all references to Project Gutenberg:
+
+1.E.1. The following sentence, with active links to, or other immediate
+access to, the full Project Gutenberg-tm License must appear prominently
+whenever any copy of a Project Gutenberg-tm work (any work on which the
+phrase "Project Gutenberg" appears, or with which the phrase "Project
+Gutenberg" is associated) is accessed, displayed, performed, viewed,
+copied or distributed:
+
+This eBook is for the use of anyone anywhere at no cost and with
+almost no restrictions whatsoever. You may copy it, give it away or
+re-use it under the terms of the Project Gutenberg License included
+with this eBook or online at www.gutenberg.org
+
+1.E.2. If an individual Project Gutenberg-tm electronic work is derived
+from the public domain (does not contain a notice indicating that it is
+posted with permission of the copyright holder), the work can be copied
+and distributed to anyone in the United States without paying any fees
+or charges. If you are redistributing or providing access to a work
+with the phrase "Project Gutenberg" associated with or appearing on the
+work, you must comply either with the requirements of paragraphs 1.E.1
+through 1.E.7 or obtain permission for the use of the work and the
+Project Gutenberg-tm trademark as set forth in paragraphs 1.E.8 or
+1.E.9.
+
+1.E.3. If an individual Project Gutenberg-tm electronic work is posted
+with the permission of the copyright holder, your use and distribution
+must comply with both paragraphs 1.E.1 through 1.E.7 and any additional
+terms imposed by the copyright holder. Additional terms will be linked
+to the Project Gutenberg-tm License for all works posted with the
+permission of the copyright holder found at the beginning of this work.
+
+1.E.4. Do not unlink or detach or remove the full Project Gutenberg-tm
+License terms from this work, or any files containing a part of this
+work or any other work associated with Project Gutenberg-tm.
+
+1.E.5. Do not copy, display, perform, distribute or redistribute this
+electronic work, or any part of this electronic work, without
+prominently displaying the sentence set forth in paragraph 1.E.1 with
+active links or immediate access to the full terms of the Project
+Gutenberg-tm License.
+
+1.E.6. You may convert to and distribute this work in any binary,
+compressed, marked up, nonproprietary or proprietary form, including any
+word processing or hypertext form. However, if you provide access to or
+distribute copies of a Project Gutenberg-tm work in a format other than
+"Plain Vanilla ASCII" or other format used in the official version
+posted on the official Project Gutenberg-tm web site (www.gutenberg.org),
+you must, at no additional cost, fee or expense to the user, provide a
+copy, a means of exporting a copy, or a means of obtaining a copy upon
+request, of the work in its original "Plain Vanilla ASCII" or other
+form. Any alternate format must include the full Project Gutenberg-tm
+License as specified in paragraph 1.E.1.
+
+1.E.7. Do not charge a fee for access to, viewing, displaying,
+performing, copying or distributing any Project Gutenberg-tm works
+unless you comply with paragraph 1.E.8 or 1.E.9.
+
+1.E.8. You may charge a reasonable fee for copies of or providing
+access to or distributing Project Gutenberg-tm electronic works provided
+that
+
+- You pay a royalty fee of 20% of the gross profits you derive from
+ the use of Project Gutenberg-tm works calculated using the method
+ you already use to calculate your applicable taxes. The fee is
+ owed to the owner of the Project Gutenberg-tm trademark, but he
+ has agreed to donate royalties under this paragraph to the
+ Project Gutenberg Literary Archive Foundation. Royalty payments
+ must be paid within 60 days following each date on which you
+ prepare (or are legally required to prepare) your periodic tax
+ returns. Royalty payments should be clearly marked as such and
+ sent to the Project Gutenberg Literary Archive Foundation at the
+ address specified in Section 4, "Information about donations to
+ the Project Gutenberg Literary Archive Foundation."
+
+- You provide a full refund of any money paid by a user who notifies
+ you in writing (or by e-mail) within 30 days of receipt that s/he
+ does not agree to the terms of the full Project Gutenberg-tm
+ License. You must require such a user to return or
+ destroy all copies of the works possessed in a physical medium
+ and discontinue all use of and all access to other copies of
+ Project Gutenberg-tm works.
+
+- You provide, in accordance with paragraph 1.F.3, a full refund of any
+ money paid for a work or a replacement copy, if a defect in the
+ electronic work is discovered and reported to you within 90 days
+ of receipt of the work.
+
+- You comply with all other terms of this agreement for free
+ distribution of Project Gutenberg-tm works.
+
+1.E.9. If you wish to charge a fee or distribute a Project Gutenberg-tm
+electronic work or group of works on different terms than are set
+forth in this agreement, you must obtain permission in writing from
+both the Project Gutenberg Literary Archive Foundation and Michael
+Hart, the owner of the Project Gutenberg-tm trademark. Contact the
+Foundation as set forth in Section 3 below.
+
+1.F.
+
+1.F.1. Project Gutenberg volunteers and employees expend considerable
+effort to identify, do copyright research on, transcribe and proofread
+public domain works in creating the Project Gutenberg-tm
+collection. Despite these efforts, Project Gutenberg-tm electronic
+works, and the medium on which they may be stored, may contain
+"Defects," such as, but not limited to, incomplete, inaccurate or
+corrupt data, transcription errors, a copyright or other intellectual
+property infringement, a defective or damaged disk or other medium, a
+computer virus, or computer codes that damage or cannot be read by
+your equipment.
+
+1.F.2. LIMITED WARRANTY, DISCLAIMER OF DAMAGES - Except for the "Right
+of Replacement or Refund" described in paragraph 1.F.3, the Project
+Gutenberg Literary Archive Foundation, the owner of the Project
+Gutenberg-tm trademark, and any other party distributing a Project
+Gutenberg-tm electronic work under this agreement, disclaim all
+liability to you for damages, costs and expenses, including legal
+fees. YOU AGREE THAT YOU HAVE NO REMEDIES FOR NEGLIGENCE, STRICT
+LIABILITY, BREACH OF WARRANTY OR BREACH OF CONTRACT EXCEPT THOSE
+PROVIDED IN PARAGRAPH F3. YOU AGREE THAT THE FOUNDATION, THE
+TRADEMARK OWNER, AND ANY DISTRIBUTOR UNDER THIS AGREEMENT WILL NOT BE
+LIABLE TO YOU FOR ACTUAL, DIRECT, INDIRECT, CONSEQUENTIAL, PUNITIVE OR
+INCIDENTAL DAMAGES EVEN IF YOU GIVE NOTICE OF THE POSSIBILITY OF SUCH
+DAMAGE.
+
+1.F.3. LIMITED RIGHT OF REPLACEMENT OR REFUND - If you discover a
+defect in this electronic work within 90 days of receiving it, you can
+receive a refund of the money (if any) you paid for it by sending a
+written explanation to the person you received the work from. If you
+received the work on a physical medium, you must return the medium with
+your written explanation. The person or entity that provided you with
+the defective work may elect to provide a replacement copy in lieu of a
+refund. If you received the work electronically, the person or entity
+providing it to you may choose to give you a second opportunity to
+receive the work electronically in lieu of a refund. If the second copy
+is also defective, you may demand a refund in writing without further
+opportunities to fix the problem.
+
+1.F.4. Except for the limited right of replacement or refund set forth
+in paragraph 1.F.3, this work is provided to you 'AS-IS' WITH NO OTHER
+WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED, INCLUDING BUT NOT LIMITED TO
+WARRANTIES OF MERCHANTIBILITY OR FITNESS FOR ANY PURPOSE.
+
+1.F.5. Some states do not allow disclaimers of certain implied
+warranties or the exclusion or limitation of certain types of damages.
+If any disclaimer or limitation set forth in this agreement violates the
+law of the state applicable to this agreement, the agreement shall be
+interpreted to make the maximum disclaimer or limitation permitted by
+the applicable state law. The invalidity or unenforceability of any
+provision of this agreement shall not void the remaining provisions.
+
+1.F.6. INDEMNITY - You agree to indemnify and hold the Foundation, the
+trademark owner, any agent or employee of the Foundation, anyone
+providing copies of Project Gutenberg-tm electronic works in accordance
+with this agreement, and any volunteers associated with the production,
+promotion and distribution of Project Gutenberg-tm electronic works,
+harmless from all liability, costs and expenses, including legal fees,
+that arise directly or indirectly from any of the following which you do
+or cause to occur: (a) distribution of this or any Project Gutenberg-tm
+work, (b) alteration, modification, or additions or deletions to any
+Project Gutenberg-tm work, and (c) any Defect you cause.
+
+
+Section 2. Information about the Mission of Project Gutenberg-tm
+
+Project Gutenberg-tm is synonymous with the free distribution of
+electronic works in formats readable by the widest variety of computers
+including obsolete, old, middle-aged and new computers. It exists
+because of the efforts of hundreds of volunteers and donations from
+people in all walks of life.
+
+Volunteers and financial support to provide volunteers with the
+assistance they need, is critical to reaching Project Gutenberg-tm's
+goals and ensuring that the Project Gutenberg-tm collection will
+remain freely available for generations to come. In 2001, the Project
+Gutenberg Literary Archive Foundation was created to provide a secure
+and permanent future for Project Gutenberg-tm and future generations.
+To learn more about the Project Gutenberg Literary Archive Foundation
+and how your efforts and donations can help, see Sections 3 and 4
+and the Foundation web page at http://www.pglaf.org.
+
+
+Section 3. Information about the Project Gutenberg Literary Archive
+Foundation
+
+The Project Gutenberg Literary Archive Foundation is a non profit
+501(c)(3) educational corporation organized under the laws of the
+state of Mississippi and granted tax exempt status by the Internal
+Revenue Service. The Foundation's EIN or federal tax identification
+number is 64-6221541. Its 501(c)(3) letter is posted at
+http://pglaf.org/fundraising. Contributions to the Project Gutenberg
+Literary Archive Foundation are tax deductible to the full extent
+permitted by U.S. federal laws and your state's laws.
+
+The Foundation's principal office is located at 4557 Melan Dr. S.
+Fairbanks, AK, 99712., but its volunteers and employees are scattered
+throughout numerous locations. Its business office is located at
+809 North 1500 West, Salt Lake City, UT 84116, (801) 596-1887, email
+business@pglaf.org. Email contact links and up to date contact
+information can be found at the Foundation's web site and official
+page at http://pglaf.org
+
+For additional contact information:
+ Dr. Gregory B. Newby
+ Chief Executive and Director
+ gbnewby@pglaf.org
+
+
+Section 4. Information about Donations to the Project Gutenberg
+Literary Archive Foundation
+
+Project Gutenberg-tm depends upon and cannot survive without wide
+spread public support and donations to carry out its mission of
+increasing the number of public domain and licensed works that can be
+freely distributed in machine readable form accessible by the widest
+array of equipment including outdated equipment. Many small donations
+($1 to $5,000) are particularly important to maintaining tax exempt
+status with the IRS.
+
+The Foundation is committed to complying with the laws regulating
+charities and charitable donations in all 50 states of the United
+States. Compliance requirements are not uniform and it takes a
+considerable effort, much paperwork and many fees to meet and keep up
+with these requirements. We do not solicit donations in locations
+where we have not received written confirmation of compliance. To
+SEND DONATIONS or determine the status of compliance for any
+particular state visit http://pglaf.org
+
+While we cannot and do not solicit contributions from states where we
+have not met the solicitation requirements, we know of no prohibition
+against accepting unsolicited donations from donors in such states who
+approach us with offers to donate.
+
+International donations are gratefully accepted, but we cannot make
+any statements concerning tax treatment of donations received from
+outside the United States. U.S. laws alone swamp our small staff.
+
+Please check the Project Gutenberg Web pages for current donation
+methods and addresses. Donations are accepted in a number of other
+ways including checks, online payments and credit card donations.
+To donate, please visit: http://pglaf.org/donate
+
+
+Section 5. General Information About Project Gutenberg-tm electronic
+works.
+
+Professor Michael S. Hart is the originator of the Project Gutenberg-tm
+concept of a library of electronic works that could be freely shared
+with anyone. For thirty years, he produced and distributed Project
+Gutenberg-tm eBooks with only a loose network of volunteer support.
+
+
+Project Gutenberg-tm eBooks are often created from several printed
+editions, all of which are confirmed as Public Domain in the U.S.
+unless a copyright notice is included. Thus, we do not necessarily
+keep eBooks in compliance with any particular paper edition.
+
+
+Most people start at our Web site which has the main PG search facility:
+
+ http://www.gutenberg.org
+
+This Web site includes information about Project Gutenberg-tm,
+including how to make donations to the Project Gutenberg Literary
+Archive Foundation, how to help produce our new eBooks, and how to
+subscribe to our email newsletter to hear about new eBooks.